Bombay High Court
WP/599/2005 of MAHARASHTRA STATE ELECTRICITY BOARD Vs MAHARASHTRA ELECTRICITY REGULATORY COMMISSION AND ORS on 24 December 2004
IN THE HIGH COURT OF
((-1-))
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
WRIT PETITION (LODGING) NO.118 OF 2005
Maharashtra State Electricity
Board Petitioner
versus
Maarashtra Electricity Regulatory
Commission and others Respondents
Ms.Deepa Chavan i/by Little & Co; adv. for petitioner.
Mr.Rajiv Mane, AGP for respondent no.1.
CORAM : H.L.GOKHALE AND
S.C.DHARMADHIKARI, JJ.
DATE : 14th February 2005
PC :
Citations and Judicial Treatment
Cited by
0
Decisions in the index citing it
Cites
0
Decisions referred to
In this index
0
Of the decisions it cites
Overruled / Questioned
0
No negative treatment found
Loading the citing and cited decisions…
This judgment in the centre: on the left the decisions it cites, on the right the decisions citing it. Colour is the treatment; choose a decision to open it.
1. Heard Ms.Chavan in support of this petition.
She seeks leave to add three more parties to the present petition namely a Consumer Group by name Prayas, Mumbai Grahak Manch and Thane-Belapur Industries Association. She also seeks to add a copy of the order passed on 1st February 2005 to this petition as Exhibit-E. There is also a request to add certain averments with respect to this added exhibit and prayer seeking that no further steps be taken in pursuance of this ((-2-))
order. Ms.Chavan states that amendments will be carried out by tomorrow. Notice to the added parties as well as to respondent nos.3 and 4
returnable on 7th March 2005. In the mean while and until further orders, first respondent MERC
will not take any further steps in pursuance of the order passed on 1st February 2005 under section 142 of the Electricity Act, 2003 on the basis of alleged breach of directions given earlier.
(H.L.GOKHALE, J.)