Kerala High Court
MACA/57/2011 of SREEKUMAR G. Vs DR.PONNUS SAM on 30 December 2011
THE LOK ADALAT ORGANISED BY THE HIGH COURT LEGAL SERVICES COMMITTEE AT ERNAKULAM PRESENT : THE HONOURABLE MR. JUSTICE K.JOHN MATHEW (RETD.JUDGE) AND SMT.K.SREELATHA DEVI (ADVOCATE) FRIDAY, THE 30TH DECEMBER 2011 / 9TH POUSHA 1933 MACA.No. 57 of 2011() --------------------- OPMV.181/2006 of MOTOR
BEFORE THE LOK ADALAT
ORGANISED BY THE HIGH COURT LEGAL SERVICES COMMITTEE
AT ERNAKULAM
PRESENT :
THE HONOURABLE MR. JUSTICE K.JOHN MATHEW (RETD.JUDGE)
AND
SMT.K.SREELATHA DEVI (ADVOCATE)
FRIDAY, THE 30TH DECEMBER 2011 / 9TH POUSHA 1933
MACA.No. 57 of 2011()
---------------------
OPMV.181/2006 of MOTOR ACCIDENT CLAIMS TRIBUNAL, PUNALUR
....................
APPELLANT/PETITIONER
-----------------------------------
SREEKUMAR G., S/O.GANGADHARAN PILLAI,
KRISHNA VILASOM, THEVALAPPURAM P.O.,
PUTHOOR, KOTTARAKKARA.
BY ADV. SRI.ANCHAL C.VIJAYAN
RESPONDENTs/ RESPONDENTS
-------------------------------------------
Citations and Judicial Treatment
Cited by
0
Decisions in the index citing it
Cites
0
Decisions referred to
In this index
0
Of the decisions it cites
Overruled / Questioned
0
No negative treatment found
Loading the citing and cited decisions…
This judgment in the centre: on the left the decisions it cites, on the right the decisions citing it. Colour is the treatment; choose a decision to open it.
1. DR.PONNUS SAM, S/O.SAM,
KUTHIRANCHIRA, PUNALUR-691501
2. NATIONAL INSURANCE CO. LTD.,
DIVISIONAL OFFICE, THIRUVANANTHAPURAM-695001
R2 ADV. SMT.RAJI T.BHASKAR
THIS MOTOR ACCIDENT CLAIMS APPEAL HAVING COME UP FOR
DETERMINATION BEFORE THE LOK ADALATH ON 30/12/2011, THE ADALATH ON THESAME DAY DELIVERED THE FOLLOWING.
smm
K.JOHN MATHEW (RETD. JUDGE)AND
K .SREELATHA DEVI (ADVOCATE)
---------------------------------
MACA No. 57 OF 2011--------------------------------- Dated this the 30[th] day of December, 2011
A W A R D
The parties have settled the dispute in this appeal.The 2[nd] respondent, Insurance Company has agreed to payand the appellants have agreed to receive an additionalcompensation of Rs. 45,000/- in full and final settlement ofthe claim within two months from this date. In case theamount is not paid within two months, the 2[nd] respondentwill also be liable to pay interest at the rate of 9% perannum from this date till payment. The appeals aredisposed of as above and an award is passed accordingly.
Sd/- K.JOHN MATHEW(RETD.JUDGE)
Sd/- K. SREELATHA DEVI (ADVOCATE)
True copy
P.A. To Judge.
smm