SRI JUSTICE L.NARASIMHA REDDY W.P.No.27707 of 2005 Date:28.12.2005 Between: D.L.Sadasiva Reddy, s/o Late Lakshman Reddy, 4-5-7/1, 4th Ward, Indiranagar, Madanapalli, Chittoor istrict …. Petitioner A n d The Secretary, State Transport Authority, BRKR Buildings, Hyderabad-A.P.

THE HON’BLE SRI JUSTICE L.NARASIMHA REDDY

W.P.No.27707 of 2005

Date:28.12.2005

Between:

D.L.Sadasiva Reddy, s/o Late

Lakshman Reddy, 4-5-7/1, 4[th] Ward,

Indiranagar, Madanapalli,

Chittoor istrict

A n d

The Secretary,State Transport Authority,BRKR Buildings, Hyderabad-A.P.

…. Petitioner

… Respondent

THE HON’BLE SRI JUSTICE L.NARASIMHA REDDY

W.P.No.27707 of 2005

Citations and Judicial Treatment

No citing decisions in the index yet

Cited by

0

Decisions in the index citing it

Cites

0

Decisions referred to

In this index

0

Of the decisions it cites

Overruled / Questioned

0

No negative treatment found

Loading the citing and cited decisions…

ORDER:

Petitioner states that he submitted an application for grant of pakka permit on theroad from Proddutur to Bangalore. It is stated that when the application was notconsidered he approached this Court by filing a writ petition and thereafter, theapplication was placed before the State Transport Authority at its meeting held on19.3.2005. It is represented that no orders have been communicated so far.

Petitioner contends that having regard to the need and urgency, he filed applicationfor grant of temporary permit on 19.12.2005 and complains that no action is takenthereon.

Heard the learned counsel for the petitioner and the learned Government Pleader forTransport.

By its very nature, an application for grant of pukka permit needs to be considered byState Transport Authority and it is likely to take quite some time. Obviously, toreduce the rigour on account of such delays, the Motor Vehicles Act and the Rulesmade thereunder provide for grant of temporary permits and such power is conferredupon the Secretary, State Transport Authority or the Regional Transport Authority, asthe case may be.

In the instant case, the application of the petitioner for grant of permit had alreadybeen dealt with by the State Transport Authority, but the result thereof is notcommunicated. In such an event, there should not be any difficulty for the Secretary,State Transport Authority in considering the application of the petitioner for grant oftemporary permit. The application cannot be kept pending indefinitely.

Hence, the writ petition is disposed of directing the respondent to dispose of theapplication of the petitioner within a period of two weeks from the date of receipt ofthis order. There shall be no order as to costs.

__________

28.12.2005

You have used today's free searches. Sign in, for free, to keep searching without a limit.

Compass reads the judgments for you and finds the paragraphs for and against your question. Sign in to use it.

My Vault follows judgments for you and records every later decision that cites them. Sign in to keep one.

Sign in to download the court's PDF. The full text stays free to read here.

Sign in, for free, to download the court copy. Reading the full text here stays open to everyone.

Search and read Indian judgments without limits, save them to My Vault and find the relevant paragraphs with Compass.

Open the sign-in page instead