Telangana High Court

WP/27300/2005 of G.Anjaneyulu Vs Municipal Corporation of Hyderabad, rep.by its on 28 December 2005

Cites 0, Cited by 0

SRI JUSTICE V.V.S.RAO WRIT PETITION No.27300 of 2005 28.12.2005 Between: G.Anjaneyulu, S/o.Venkatesam … Petitioner AND The Commissioner, Municipal Corporation of Hyderabad … Respondent THE HON’BLE SRI JUSTICE V.V.S.RAO WRIT PETITION No.27300 of 2005 ORDER: The

THE HON’BLE SRI JUSTICE V.V.S.RAO

WRIT PETITION No.27300 of 2005

28.12.2005

Between:G.Anjaneyulu, S/o.Venkatesam

AND

The Commissioner, Municipal Corporation of Hyderabad … Petitioner … Respondent THE HON’BLE SRI JUSTICE V.V.S.RAO

WRIT PETITION No.27300 of 2005

Citations and Judicial Treatment

No citing decisions in the index yet

Cited by

0

Decisions in the index citing it

Cites

0

Decisions referred to

In this index

0

Of the decisions it cites

Overruled / Questioned

0

No negative treatment found

Loading the citing and cited decisions…

ORDER:

The petitioner purchased a house bearing No.1-9-113/29 situated atSeetharamanagar near Vidyanagar, Hydeabad. As the said house required repairsand was in a collapsible condition, he submitted an explanation to the respondentCorporation seeking sanction of building permission. According to the petitioner, theapplication was considered by the Building committee, which duly recommendedthe case and in spite of the same, the respondent did not issue necessary ordersgranting building permission. Therefore, the present writ petition seeking a directionto the respondent to sanction the building approval.

Heard Mrs.G.Madhuri representing Sri N. Gurugopal, the learned Counsel for thepetitioner and the learned Standing Counsel Sri Ghanta Rama Rao. A perusal of theletter dated 18/21.3.2005 addressed by the Chief City Planner to the Chief PlanningOfficer, Hyderabad Urban Development Authority (HUDA) would show that theBuilding committee has recommended the case of the petitioner, but the latterobjected for granting building permission on the ground that the petitioner’spremises is a mandatory open space in the layout. At that stage, the Chief CityPlanner sought clarification from HUDA and the matter is pending. Therefore, it is forthe Municipal Corporation to seek necessary clarification and pass appropriateorders on the application of the petitioner for building permission. The learnedStanding Counsel does not dispute this position. Therefore, the writ petition isdisposed of directing the respondent Corporation to pass appropriate orders on theapplication made by the petitioner seeking permission for construction of ground andfirst floor residential house within a period of two weeks from the date of receipt of acopy of this order.

The writ petition, with the above observations and directions, is accordingly disposed of. No costs.

December 28, 2005. (V.V.S. RAO,J)

YS

_____________

You have used today's free searches. Sign in, for free, to keep searching without a limit.

Compass reads the judgments for you and finds the paragraphs for and against your question. Sign in to use it.

My Vault follows judgments for you and records every later decision that cites them. Sign in to keep one.

Sign in to download the court's PDF. The full text stays free to read here.

Sign in, for free, to download the court copy. Reading the full text here stays open to everyone.