Telangana High Court

WP/25180/2004 of G. Srikar Rao, Vs The Suprentending Engineer, Operation Circle, North, on 31 December 2004

Cites 0, Cited by 0

HIGH COURT OF JUDICATURE, ANDHRA PRADESH AT HYDERABAD (Special Original Jurisdiction) FRIDAY, THE THIRTY FIRST DAY OF DECEMBER TWO THOUSAND AND FOUR PRESENT THE HON'BLE MR JUSTICE L.NARASIMHA REDDY WRIT PETITION NO : 25180 of 2004 Between: G. Srikar Rao, S/o. G. Keshava Rao, (Late), R/o. 5-96/1,

IN THE HIGH COURT OF JUDICATURE, ANDHRA PRADESH AT HYDERABAD

(Special Original Jurisdiction)

FRIDAY, THE THIRTY FIRST DAY OF DECEMBERTWO THOUSAND AND FOUR

PRESENT

THE HON'BLE MR JUSTICE L.NARASIMHA REDDY

WRIT PETITION NO : 25180 of 2004

Between:

G. Srikar Rao, S/o. G. Keshava Rao, (Late), R/o. 5-96/1, Mosapet, Hyderabad.

..... PETITIONER

AND

The Superintending Engineer, Operation Circle, North, APCPDCL, Mint Compound, Hyderabad.

.....RESPONDENT

Petition under Article 226 of the Constitution of India praying that in thecircumstances stated in the Affidavit filed herein the High Court will be pleased toissue a writ of mandamus declaring the proceedings dt. 3.12.2004 issued by therespondent bearing LR.No. SE/OP/north/Hyd/ AO(Rev)CRS/JAO/D.No.1633 asillegal and unjustified.

Counsel for the Petitioner:MR.J.C.FRANCIS

Counsel for the Respondent: SMT.M.VINOBHA DEVI

The Court made the following :

Citations and Judicial Treatment

No citing decisions in the index yet

Cited by

0

Decisions in the index citing it

Cites

0

Decisions referred to

In this index

0

Of the decisions it cites

Overruled / Questioned

0

No negative treatment found

Loading the citing and cited decisions…

ORDER:

The petitioner is a consumer of electricity. The Divisional Engineer/Operations, City-IV, Hyderabad, issued an order of final assessment dated 29.11.1999 holding thatthe petitioner is liable to pay a sum of Rs.83,073/- towards back billing. Aggrieved bythe same, the petitioner preferred an appeal before the respondent herein. Throughletter dated 03.12.2004, the petitioner was required to pay a sum of Rs.41,537/-,representing half of the amount covered by the order of final assessment as acondition precedent for entertaining the appeal. The petitioner challenges the same.

Heard learned counsel for the petitioner and learned Standing Counsel for therespondent.

The petitioner availed the remedy of appeal against the order of final assessment.The terms and conditions of supply provided for payment of half of the amountwhenever an appeal is preferred against the order of final assessment.

The petitioner states that he is in financial difficulty and the order of final assessmentitself was of the year 1999.

Taking the totality of the circumstances into account, the writ petition isdisposed of directing that in case, the petitioner deposits a sum of Rs.25,000/-(Rupees twenty five thousands only) within three weeks from today, the respondentshall entertain the appeal and dispose of the same in accordance with law. No costs.

_________

To

1. The Superintending Engineer, Operation Circle, North, APCPDCL, Mint Compound, Hyderabad.

2.2CD copies

You have used today's free searches. Sign in, for free, to keep searching without a limit.

Compass reads the judgments for you and finds the paragraphs for and against your question. Sign in to use it.

My Vault follows judgments for you and records every later decision that cites them. Sign in to keep one.

Sign in to download the court's PDF. The full text stays free to read here.

Sign in, for free, to download the court copy. Reading the full text here stays open to everyone.

Search and read Indian judgments without limits, save them to My Vault and find the relevant paragraphs with Compass.

Open the sign-in page instead