MR JUSTICE L. NARASIMHA REDDY Writ Petition No.29229 of 2009 ORDER: The subject matter of this writ petition is squarely covered by a common order passed by this Court in W.P.No.11269 of 2009 and batch dated 22.10.2009. Following the same, this writ petition is also disposed of ,
THE HON’BLE MR JUSTICE L. NARASIMHA REDDYWrit Petition No.29229 of 2009
Citations and Judicial Treatment
Cited by
0
Decisions in the index citing it
Cites
0
Decisions referred to
In this index
0
Of the decisions it cites
Overruled / Questioned
0
No negative treatment found
Loading the citing and cited decisions…
This judgment in the centre: on the left the decisions it cites, on the right the decisions citing it. Colour is the treatment; choose a decision to open it.
ORDER:
The subject matter of this writ petition is squarely covered by acommon order passed by this Court in W.P.No.11269 of 2009 andbatch dated 22.10.2009.
Following the same, this writ petition is also disposed of,directing that: - (a)the respondents shall include 1% cess in the estimatesfor the works which they propose to undertake, ifthe work continues for or beyond twelve monthsand involves engagement of 10 workers or more;andfor the works which they propose to undertake, ifthe work continues for or beyond twelve monthsand involves engagement of 10 workers or more;and (b)the respondents shall not deduct any amount towardscess, unless the corresponding amount isincluded in the estimates.cess, unless the corresponding amount isincluded in the estimates.
There shall be no order as to costs.
Dt.31-12-2009.GJ