SRI JUSTICE P. NAVEEN RAO WRIT PETITION No.45737 OF 2016 Dated:29.12.2016 Between: Ponnepalli Venkata Chalapathi, S/o. Late P. Gonvidaiah, Aged about 43 years, Occ: Advocate, R/o.D.No.9733, Gandla Street, Bahadurpet, Srikalahasti, Chittoor District .. Petitioner And Srikalahasti

Citations and Judicial Treatment

No citing decisions in the index yet

Cited by

0

Decisions in the index citing it

Cites

0

Decisions referred to

In this index

0

Of the decisions it cites

Overruled / Questioned

0

No negative treatment found

Loading the citing and cited decisions…

THE HON’BLE SRI JUSTICE P. NAVEEN RAO

WRIT PETITION No.45737 OF 2016

Dated:29.12.2016

Between:

Ponnepalli Venkata Chalapathi, S/o. Late P. Gonvidaiah, Aged about 43 years, Occ: Advocate, R/o.D.No.9733, Gandla Street, Bahadurpet, Srikalahasti, Chittoor District .. Petitioner

And

Srikalahasti Municipality, Srikalahasti, Chittoor District, Rep., by its Commissioner and others .. Respondents The Court made the following:

THE HON’BLE SRI JUSTICE P. NAVEEN RAO

WRIT PETITION No.45737 OF 2016

ORDER:

Heard. With the consent of learned counsel for the parties, the Writ Petition is being disposed of at the stage of admission.

2. The petitioner alleges that his neighbours, the unofficial respondents herein, are undertaking construction without leaving any setbacks as per the norms of the Municipality and without obtaining building permission from the 1[st] respondent – Municipality. His grievance is that though he made a representation dated 08.12.2016 bringing the said fact to the notice of the authority concerned, no action has been taken so far. Hence, this writ petition.

3. Learned Standing Counsel for the 1[st] respondent – Municipality, on instructions, submits that the building permission application was made by the unofficial respondents through online portal and necessary permission was granted and they are undertaking construction in accordance with the building permission granted to them. He further submits that the construction is at the stage of digging of foundation pits and raising of pillars and thus there is no truth in the allegation made by the petitioner that the construction is in advance stage and setbacks are not observed.

4. In the light of the submission made by the learned Standing Counsel, the Writ Petition does not survive and the same is liable to be dismissed.

5. The Writ Petition is accordingly dismissed. However, it is made clear that the 1[st] respondent – Municipality shall ensure that the unofficial respondents shall comply with the building permission norms and do not deviate from the permission granted to them causing hardship to the neighbours. There shall be no order as to costs.

Miscellaneous Petitions, if any, pending in this Writ Petition shall stand closed.

____________________

P. NAVEEN RAO, J Date:29.12.2016 KH

You have used today's free searches. Sign in, for free, to keep searching without a limit.

Compass reads the judgments for you and finds the paragraphs for and against your question. Sign in to use it.

My Vault follows judgments for you and records every later decision that cites them. Sign in to keep one.

Sign in to download the court's PDF. The full text stays free to read here.

Sign in, for free, to download the court copy. Reading the full text here stays open to everyone.

Search and read Indian judgments without limits, save them to My Vault and find the relevant paragraphs with Compass.

Open the sign-in page instead