Telangana High Court
WP/25347/2000 of Bhukya Lakpathi, Vs The Executive Engineer (E.M.A.), on 26 December 2006
Ms. JUSTICE G.ROHINI WRIT PETITION NO: 25347 of 2000 Dated: 26-12-2006 Between: Bhukya Lakpathi ..... PETITIONER AND The Executive Engineer (E.M.A.), Eturnagaram, Warangal District and 3 others. .....RESPONDENTS THE HON'BLE Ms. JUSTICE G.ROHINI WRIT PETITION NO: 25347 of 2000 O R D E R: While
Citations and Judicial Treatment
Cited by
0
Decisions in the index citing it
Cites
0
Decisions referred to
In this index
0
Of the decisions it cites
Overruled / Questioned
0
No negative treatment found
Loading the citing and cited decisions…
This judgment in the centre: on the left the decisions it cites, on the right the decisions citing it. Colour is the treatment; choose a decision to open it.
Conclusion
THE HON'BLE Ms. JUSTICE G.ROHINI
WRIT PETITION NO: 25347 of 2000
Between:
Dated: 26-12-2006
Bhukya Lakpathi
AND
..... PETITIONER
The Executive Engineer (E.M.A.),Eturnagaram, Warangal District and 3 others.
.....RESPONDENTS
THE HON'BLE Ms. JUSTICE G.ROHINI
WRIT PETITION NO: 25347 of 2000
O R D E R:
While directing Rule Nisi, by order dated, 20-12-2000, this Courtgranted interim stay of allotment of work to third party till the applicationdated 07-09-2000 made by the petitioner is considered and disposedof.
In view of the said interim order, no further adjudication isnecessary in the writ petition and accordingly the same is disposed of. No costs.
______________
G. ROHINI, J
Dated: 26-12-2006KLP