Telangana High Court
WP/29411/2009 of M/S. MAYTAS INFRA PVT LTD. Vs The Secretary to Govt., Finance and Planning ( Works AND on 31 December 2009
COURT OF JUDICATURE OF ANDHRA PRADESH AT HYDERABAD THURSDAY, THIS THE 31st DAY OF DECEMBER, 2009 W.P.No.29411 of 2009 BETWEEN: M/s.Maytas Infra Pvt Ltd., rep by its Authorised Signatory Yaragorla Tagore ... PETITIONER(S) and The Secretary to Govt., Finance & Planning (Works and Projects)
IN THE HIGH COURT OF JUDICATURE OF ANDHRA PRADESHAT HYDERABAD
THURSDAY, THIS THE 31[st] DAY OF DECEMBER, 2009
W.P.No.29411 of 2009
BETWEEN:
M/s.Maytas Infra Pvt Ltd., rep by its Authorised Signatory YaragorlaTagore
and
... PETITIONER(S)
The Secretary to Govt., Finance & Planning (Works and Projects)Department, Secretariat Buildings, Hyderabad and others …RESPONDENT(S)
THE HON’BLE SRI JUSTICE L.NARASIMHA REDDY
W.P.No.29411 of 2009
ORDER:
The subject matter of this writ petition is squarely covered by acommon order passed by this Court in W.P.No.11269 of 2009 andbatch dated 22.10.2009.
Following the same, this writ petition is also disposed ofdirecting that:- (a)the respondents shall include 1% cess in the estimatesfor the works which they propose to undertake, if thework continues for or beyond twelve months andinvolves engagement of 10 workers or more; andfor the works which they propose to undertake, if thework continues for or beyond twelve months andinvolves engagement of 10 workers or more; and (b)the respondents shall not deduct any amount towardscess, unless the corresponding amount is included inthe estimates.cess, unless the corresponding amount is included inthe estimates.
There shall be no order as to costs.
__________________________
L.NARASIMHA REDDY, J
31[st] December 2009
CVRK