MR JUSTICE V.ESWARAIAH WRIT PETITION No: 27412 of 2005 DATED: 23.12.2005 Between: Bokka Surya Rao … Petitioner. AND The Divisional Engineer, Andhra Pradesh Eastern Power Distribution Company Limited (APEPDCL), Nidedavolu, West Godavari District & another. … Respondents

Citations and Judicial Treatment

No citing decisions in the index yet

Cited by

0

Decisions in the index citing it

Cites

0

Decisions referred to

In this index

0

Of the decisions it cites

Overruled / Questioned

0

No negative treatment found

Loading the citing and cited decisions…

THE HON'BLE MR JUSTICE V.ESWARAIAH

WRIT PETITION No: 27412 of 2005

DATED: 23.12.2005

Between:

Bokka Surya Rao… Petitioner.ANDThe Divisional Engineer,Andhra Pradesh Eastern Power DistributionCompany Limited (APEPDCL),Nidedavolu, West Godavari District & another.… Respondents

ORDER:-

This writ petition is filed to declare the action of the respondents in not taking stepsfor transferring the service electricity connections bearing Nos.276 and 280 in theagricultural land belonging to the petitioner situated in Sy.No.320 of Bheemuruvillage of Gopalapuram Mandal, West Godavari District as illegal, arbitrary andunjust.

Learned counsel appearing for the petitioner submits that the petitioner haspurchased agricultural lands to an extent of Acs.20-00 in Sy.No.320 of BheemuruVillage of Gopalapuram Mandal, West Godavari District under a registered saledeed, dated 20.11.2003, and the revenue authorities also entered his name in therevenue records and issued pattadar pass book and title deeds. It is also submittedthat there are two electricity service connections bearing Nos.276 and 280 in thesaid lands. As the said service connections stand in the name of the vendor viz.,Siyoratan Dharmiya, S/o. Gouri Shanker Dharmiya and as the entire land has beentransferred to the petitioner along with the service connections, petitioner filed anapplication to the respondents on 14.07.2005 for transferring the said electricityservice connections to his name. Thereafter, the petitioner filed the requireddocuments and prescribed proformae, but the said service connections have notbeen transferred in his name so far and without considering the said application, therespondents are threatening to take coercive steps for disconnection of the electricityservice connections.

Heard both the counsel.

Having regard to the facts and circumstances of the case, the 1[st] respondent isdirected to consider and dispose of the said transfer application of the petitioner inaccordance with law, and till then, no coercive steps for disconnection of the saidservice connections shall be taken.

Accordingly, the writ petition is disposed of. No order as to costs.

________________________

23.12.2005

Note: Issue CC in three days.

B/o.ES

You have used today's free searches. Sign in, for free, to keep searching without a limit.

Compass reads the judgments for you and finds the paragraphs for and against your question. Sign in to use it.

My Vault follows judgments for you and records every later decision that cites them. Sign in to keep one.

Sign in to download the court's PDF. The full text stays free to read here.

Sign in, for free, to download the court copy. Reading the full text here stays open to everyone.

Search and read Indian judgments without limits, save them to My Vault and find the relevant paragraphs with Compass.

Open the sign-in page instead