JUDICATURE AT ALLAHABAD WRIT - C No. - 38575 of 2026 Court No. - 29 HON'BLE SIDDHARTHA VARMA, J. HON'BLE KUNAL RAVI SINGH, J. 1. The contention of learned Counsel for the petitioner is that a final notice was given to the petitioner was dated 31.7.2021. Thereafter, another notice dated 13.8.2021

HIGH COURT OF JUDICATURE AT ALLAHABAD

WRIT - C No. - 38575 of 2026

Court No. - 29

HON'BLE SIDDHARTHA VARMA, J.

HON'BLE KUNAL RAVI SINGH, J.

Citations and Judicial Treatment

No citing decisions in the index yet

Cited by

0

Decisions in the index citing it

Cites

0

Decisions referred to

In this index

0

Of the decisions it cites

Overruled / Questioned

0

No negative treatment found

Loading the citing and cited decisions…

1. The contention of learned Counsel for the petitioner is that a final notice was given to the petitioner was dated 31.7.2021. Thereafter, another notice dated 13.8.2021 was sent to the petitioner. The final order, thereafter, was passed for demolition on 2.12.2021.

2. It is the case of the petitioner that ever since 2021 till 2026, the Prayagraj Development Authority slept over the matter and, therefore, the petitioner was of the opinion that there was a possibility that they might have waived the notice and the order. He, therefore, submits that now when the order had been passed on 20.8.2026, the petitioner ought to have been given one more opportunity by way of notice to be issued by Prayagraj Development Authority.

3. Learned Counsel appearing for Prayagraj Development Authority Sri Darshan Gupta states that from the record it is evident that petitioner has submitted a reply dated 25.8.2026. From the record, we also find that reply of the petitioner is there on record dated 25.8.2026.

4. Learned Counsel for Prayagraj Development Authority further states that the final order has been passed on 2.12.2021 and if the petitioner is aggrieved by the said order, he may file an appeal under Section 27 (2) of the U.P. Urban Planning and Development Act, 1973.

5. Considering the rival submissions, we are of he view that if the Versus Counsel for Petitioner(s) : Kuldeep Kumar Vishwakarma, Sandeep Kumar Vishwakarma Counsel for Respondent(s) : C.S.C., Darshan Gupta Rambabu Patel And Another .....Petitioner(s) State Of U.P. And 2 Others .....Respondent(s)

petitioner files an appeal within a period of 2 weeks, the delay in filing the appeal be condoned and the appeal be decided within 2 months thereafter.

6. For a period of 3 months, no coercieve action shall be taken against the petitioner.

7. With the aforesaid observations, the writ petition is disposed of. September 24, 2026 Irshad WRIC No. 38575 of 2026 2 (Kunal Ravi Singh,J.) (Siddhartha Varma,J.) Digitally signed by :- IRSHAD AHMAD SIDDIQUI High Court of Judicature at Allahabad

You have used today's free searches. Sign in, for free, to keep searching without a limit.

Compass reads the judgments for you and finds the paragraphs for and against your question. Sign in to use it.

My Vault follows judgments for you and records every later decision that cites them. Sign in to keep one.

Sign in to download the court's PDF. The full text stays free to read here.

Sign in, for free, to download the court copy. Reading the full text here stays open to everyone.

Search and read Indian judgments without limits, save them to My Vault and find the relevant paragraphs with Compass.

Open the sign-in page instead