IN THE HIGH COURT OF JUDICATURE AT BOMBAY BENCH AT AURANGABAD WRIT PETITION NO.13721 OF 2026 DATTATRAYA ANANDRAO INGLE VERSUS THE STATE OF MAHARASHTRA THROUGH THE SECRETARY AND OTHERS ... Advocate for the Petitioner : Mr. Shashikant E. Shekade AGP for Respondents: Mr. N.D. Batule ...

1 45.WP.13721.26.odt

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

BENCH AT AURANGABAD

WRIT PETITION NO.13721 OF 2026

DATTATRAYA ANANDRAO INGLE

VERSUS

THE STATE OF MAHARASHTRA THROUGH

THE SECRETARY AND OTHERS

...

Advocate for the Petitioner : Mr. Shashikant E. Shekade AGP for Respondents: Mr. N.D. Batule

...

CORAM

: NITIN B. SURYAWANSHI AND

ABASAHEB D. SHINDE, JJ.

DATE

: 12.10.2026

PER COURT:

Citations and Judicial Treatment

No citing decisions in the index yet

Cited by

0

Decisions in the index citing it

Cites

0

Decisions referred to

In this index

0

Of the decisions it cites

Overruled / Questioned

0

No negative treatment found

Loading the citing and cited decisions…

1. This is yet another case of agriculturist, who has not been paid compensation for 19 years. The possession of land of petitioner was taken on 16.08.2007. Private negotiations were carried out. Storage tank was constructed. Contractors are also paid their bills. After about more than 19 years, respondent No.4 submitted a proposal for acquisition to the Collector. On 19.06.2025, the final award is delivered. Despite the final award, the District Collector failed to deposit the amount of statutory interest under Section 80 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (for short, ‘the Act, 2013’). 2026:BHC-AUG:48677-DB

2 45.WP.13721.26.odt

2. In view of there being no dispute as regards the sequence events narrated above, this writ petition is allowed.

3. The learned Advocate for petitioner empathetically canvasses that the present Government has lot of funds available and therefore, the payment of interest payable under Section 80 of the Act, 2013 should be made only within 15 days. The District Collector, Beed, shall ensure that the compensation to this petitioner in terms of statutory interest as is payable under Section 80 of the Act, 2013, shall be paid to him, within two months. (ABASAHEB D. SHINDE, J.) (NITIN B. SURYAWANSHI, J.) habeeb/

You have used today's free searches. Sign in, for free, to keep searching without a limit.

Compass reads the judgments for you and finds the paragraphs for and against your question. Sign in to use it.

My Vault follows judgments for you and records every later decision that cites them. Sign in to keep one.

Sign in to download the court's PDF. The full text stays free to read here.

Sign in, for free, to download the court copy. Reading the full text here stays open to everyone.

Search and read Indian judgments without limits, save them to My Vault and find the relevant paragraphs with Compass.

Open the sign-in page instead