Calcutta High Court
WPA/25744/2026 of DEBTANAYA BANERJEE Vs THE DEPUTY GENERAL MANAGER (CO HRM), INDIAN BANK AND ORS. on 18 September 2026
2026 Ct. No. 18 Ab IN THE HIGH COURT AT CALCUTTA CONSTITUTIONAL WRIT JURISDICTION APPELLATE SIDE WPA 25744 of 2026 Debtanaya Banerjee Vs. The Deputy General Manager, (CO:HRM), Indian Bank and others. --------------- Mr. Arijit Chatterjee, Mrs. Pronita Paramanya Naskar. … for the petitioner.
18.09.
Ct. No. 18
Ab
IN THE HIGH COURT AT CALCUTTA
CONSTITUTIONAL WRIT JURISDICTION
APPELLATE SIDE
WPA 25744 of 2026
Debtanaya Banerjee
Vs.
The Deputy General Manager, (CO:HRM),
Indian Bank and others.
---------------
Mr. Arijit Chatterjee,
Mrs. Pronita Paramanya Naskar.
… for the petitioner.
Mr. Shiv Mangal Singh,
Ms. Madhu Shaw.
… for the Bank.
Citations and Judicial Treatment
Cited by
0
Decisions in the index citing it
Cites
0
Decisions referred to
In this index
0
Of the decisions it cites
Overruled / Questioned
0
No negative treatment found
Loading the citing and cited decisions…
This judgment in the centre: on the left the decisions it cites, on the right the decisions citing it. Colour is the treatment; choose a decision to open it.
1. Though the affidavit of service has not been filed, the matter is taken upon in presence of Mr. Singh, learned Advocate appearing for the Bank.
2. The writ petition, as filed, is premature as the candidature of the petitioner is still being considered, in view of the fact that the biometrics of the petitioner is not found to be an exact match.
3. The respondent Bank has taken steps to ascertain genuinity of the left thumb impression of the petitioner, which has been placed on record.
4. The candidature of the petitioner has not been rejected and the respondent Bank has taken steps to ascertain the petitioner’s identity.
5. The petitioner is aggrieved that the process of ascertaining the identity has been kept pending for a rather long period of time.
6. In view thereof, the Bank Authorities are directed to complete the process within a reasonable time preferably within a period of twelve weeks from date.
7. With the afore-stated direction, the writ petition is disposed of.
8. There shall, however, be no order as to costs.
9. Urgent Photostat certified copy of this order, if applied for, be given to the parties on priority basis.