Calcutta High Court
WPA/416/2025 of SHRI.KULVINDER SINGH Vs THE CHIEF ENGINEER (CE) AND ORS. on 25 September 2026
HIGH COURT AT CALCUTTA [ CIRCUIT BENCH AT PORT BLAIR ] *** WPA/416/2025 Shri Kulvinder Singh Vs. The Chief Engineer (CE) and Ors. Mr. Siddhartha Singha … for the petitioner Mr. Rakesh Kumar … for the respondent September 25, 2026 [SR] Item No.1 1. The writ petitioner claimed to be a
IN THE HIGH COURT AT CALCUTTA
[ CIRCUIT BENCH AT PORT BLAIR ]
***
WPA/416/2025
Shri Kulvinder Singh
Vs.
The Chief Engineer (CE) and Ors.
Mr. Siddhartha Singha
… for the petitioner
Mr. Rakesh Kumar
… for the respondent
September 25, 2026
[SR]
Item No.1
Citations and Judicial Treatment
Cited by
0
Decisions in the index citing it
Cites
0
Decisions referred to
In this index
0
Of the decisions it cites
Overruled / Questioned
0
No negative treatment found
Loading the citing and cited decisions…
This judgment in the centre: on the left the decisions it cites, on the right the decisions citing it. Colour is the treatment; choose a decision to open it.
1. The writ petitioner claimed to be a contractor who executed the work of construction of a pond on some land in Campbell Bay.
2. A dispute at the instance of a third party arose in the process. The third party objected to the construction of a pond on the site, claiming that it was his land. Under such circumstances, the work was somehow hampered for some time. The Court is informed that now the issue has attained finality by disposal of MAT/44/2025 recently.
3. It is submitted by learned advocate for the writ petitioner that in view of settlement of the dispute raised by the third party, the petitioner is entitled to payment of work executed by him.
4. Learned advocate for the petitioner relied upon the work completion certificate issued by the Junior Engineer of the Construction Division, APWD, Campbell Bay.
5. Learned advocate for the respondents, on the other hand, submits that perusal of the work completion certificate reveals that the work completion certificate was subject to measurement of the works being recorded; and quality being checked by the competent authority.
6. This remaining scrutiny of the completed work therefore lies on part of the respondent authorities. It is submitted by the learned advocate for the respondents that the authorities shall proceed expeditiously for recording measurement and for conducting the quality check within a period of six weeks from date.
7. The writ petition is accordingly disposed of expecting the exercise to be completed within six weeks from date so as to facilitate consequential steps for payment of an amount found due, in accordance with law.
8. All parties are directed to act on a server copy of this order duly downloaded from the official website of this Court.
( Madhuresh Prasad, J. )