Delhi High Court

O.M.P.(I) (COMM.)/460/2026 of M/S JANDU CONSTRUCTION INDIA PVT LTD PVT Vs NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION LIMITED on 1 October 2026

Cites 0, Cited by 0

460/2026 Page 1 of 11 $~42 * IN THE HIGH COURT OF DELHI AT NEW DELHI # CNR No. DLHC010475162026 + O.M.P.(I) (COMM.) 460/2026 & I.A. 27389/2026 M/S JANDU CONSTRUCTION INDIA PVT LTD .....Petitioner Through: Mr. Jayant Mehta, Senior Advocate with Mr. Anil Kumar, Mr. V. Hariharan and Mr. Aryan

$~42

*

IN THE HIGH COURT OF DELHI AT NEW DELHI

CNR No. DLHC010475162026

+

O.M.P.(I) (COMM.) 460/2026 & I.A. 27389/2026

M/S JANDU CONSTRUCTION INDIA PVT LTD

.....Petitioner

Through:

Mr. Jayant Mehta, Senior Advocate

with Mr. Anil Kumar, Mr. V. Hariharan

and Mr. Aryan Vora, Advocates.

versus

NATIONAL HIGHWAYS AND INFRASTRUCTURE

DEVELOPMENT CORPORATION LIMITED .....Respondent Through:

Mr. Anshul Rai, Mr. Raunaq Singh and

Ms. Mallika Ranjan, Advocates.

CORAM:

HON'BLE MR. JUSTICE TUSHAR RAO GEDELA

Citations and Judicial Treatment

No citing decisions in the index yet

Cited by

0

Decisions in the index citing it

Cites

0

Decisions referred to

In this index

0

Of the decisions it cites

Overruled / Questioned

0

No negative treatment found

Loading the citing and cited decisions…

O R D E R

%

01.10.2026 I.A. 27391/2026 (Exemption)

1. This is an application filed on behalf of the petitioner under Section 151 of the Code of Civil Procedure, 1908 (hereinafter referred to as the ‘CPC’) seeking exemption from filing true typed/legible copies of the illegible/dim document nos.2 to 22.

2. Exemption allowed, subject to just exceptions. However, true typed/legible copies of the said illegible/dim documents with proper margins be filed within four weeks with an advance copy to the respondent.

3. The application stands disposed of. I.A. 27392/2026 (Seeking exemption to file lengthy list of dates and synopsis)

4. This is an application filed on behalf of the petitioner under Section 151

of CPC seeking exemption to file lengthy list of dates and synopsis.

5. For the reasons stated therein, the application is allowed.

6. The application stands disposed of. I.A. 27390/2026 (Under Order II Rule 2, CPC)

7. This is an application filed on behalf of the petitioner under Order II Rule 2 read with Section 151 of CPC seeking permission to reserve rights to amend, alter or add to the reliefs prayed for in the present petition.

8. For the reasons stated therein, the application is allowed.

9. The application is disposed of. O.M.P.(I) (COMM.) 460/2026

10. This is a petition under Section 9 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the ‘Act’) seeking interim measures of protection in terms of the prayer clauses which are extracted hereunder: “(a) Stay the operation, implementation and effect of the Temporary Suspension Order No. NHIDCL/Tripura/ Mtc./ 2026-27 dated 25.09.2026 issued by the Respondent, whereby the Petitioner has been temporarily suspended from participating in the ongoing and future bidding processes of NHIDCL, MoRTH and its implementing agencies, pending constitution of the Arbitral Tribunal and adjudication of the disputes between the parties; and (b) Restrain the Respondent, its officers, agents and representatives from giving effect to or acting upon the impugned Temporary Suspension Order dated 25.09.2026, including by treating the Petitioner as suspended, debarred or otherwise ineligible to participate in any ongoing or future tender/bidding process of NHIDCL, MoRTH or its implementing agencies, during the pendency of the present proceedings;

(c) Restrain the Respondent, during the pendency of the present Petition and the arbitral proceedings, from taking any coercive or precipitative action against the Petitioner, including termination of the Contract, invocation or encashment of Performance Security/ Additional Performance Security, risk-and-cost action, declaration of the Petitioner as a Non-Performer, debarment/blacklisting, or any other adverse action arising out of the subject matter of the present dispute, without following due process of law and without prior leave of this Hon’ble Court; (d) Pass any further or other Order(s), direction(s), which are deemed fit, reasonable and expedient in the circumstances of the case.”

11. Mr. Jayant Mehta, learned senior counsel states that the impugned notice dated 25.09.2026 issued by the respondent, taking the action of temporarily suspending the petitioner would result in the petitioner being unable to participate in ongoing/future bidding of the NHIDCL, MoRTH and its implementing agencies. It would be onerous and may lead to financial distress for the petitioner.

12. He draws attention of this Court to the MoRTH circular dated 06.10.2021 under which the impugned notice was issued, particularly to para 5 thereof, to submit that the mandatory 15 days prior notice which was required to be issued by the authorities has not been issued in the present case, thus violating the Principles of Natural Justice. He would insist that if such notice, as required, is not mandatorily provided to the petitioner, the temporary suspension would be liable to be set aside.

13. That Apart, learned senior counsel submits that though the stretch of the highway under the project implemented by the petitioner is a subject matter of the High Court of Tripura in WP(C)(PIL) No.6/2026, yet, on the direction of the learned Division Bench of the High Court of Tripura, the respondent itself requested the Central Road Research Institute (hereinafter referred to as “CRRI”) to conduct an independent survey of the entire stretch of the highway, including that of the petitioner.

14. By drawing attention of this Court to various relevant pages of the said report, learned senior counsel contends that the CSIR-CRRI Report clearly rates the work executed by the petitioner aS either good or fair and definitely not adverse. He states that in such circumstances, the respondent has no merits or any grounds as to why the petitioner’s eligibility for ongoing and future bidding should be suspended.

15. Contrary to the aforesaid arguments, learned counsel appearing on behalf of the respondent submits, at the outset, that the present petition under Section 9 itself is not maintainable on account of two facts.

16. He states that in terms of para 7 of the MoRTH circular, the petitioner has availed a review against the decision as provided under the impugned order for temporarily suspending the petitioner, which is still pending consideration before the reviewing authority. He states that under such circumstances, the petitioner is to exercise his doctrine of election as to which remedy he needs to follow and in such circumstances, the present petition would not be maintainable.

17. He also relies upon the judgement of Coordinate Bench of this Court in “NCC Limited vs. Airport Authority of India”, O.M.P.(I)(COMM) 140/2026 dated 01.07.2026, to state that Section 9 is not maintainable when it comes to an issue of debarment initiated by the authorities.

18. Learned counsel also draws attention of this Court to the Defect Cure Notice dated 17.07.2026 enclosed in the petition to state that a 60 day time-period was granted to the petitioner to cure/rectify the defects which were noticed by the authorities, however, having failed in that time-period to cure the defects, the respondent was constrained to issue the temporary suspension notice under the impugned notice dated 25.09.2026.

19. In this context, learned counsel states that the present petition has no merits and ought to be dismissed.

20. Learned counsel for the respondent also raised an issue of pecuniary jurisdiction inasmuch as he states that the entire petition of the petitioner is predicated only on the defect liability period, which is to the extent of 0.5% of the entire project, which comes to equal to or less than Rs.1 Crore. Thus, this Court may not be of the requisite pecuniary jurisdiction to entertain the present petition.

21. Be that as it may, this Court has heard learned counsel appearing on behalf of the parties.

22. It is not doubted that the order dated 25.09.2026 of temporary suspension of the petitioner has been invoked by the respondent authority in terms of para 5 of the MoRTH circular dated 06.10.2021. The operative portion of the impugned order is extracted hereunder: “Temporary Suspension:

M/s Jandu Construction India Pvt. Ltd. in JV with Maan Builders having registered office at A-21, 2nd Floor, Pushpanjali Enclave, Front of Pillar No.30, Pitampura, New-Delhi-110034, EPC Contractor of Improvement and widening to two lane with paved shoulder of road from Km 49.200 to Km 63.700 (Total length: 14.500 km) i.e. Jurichara-Bamanchara section of NH-208 (Package-III) in the state of Tripura on EPC basis, is hereby temporarily suspended from participating in ongoing/future bidding of NHIDCL, MoRTH and its implementing agencies, as applicable under the aforesaid MoRT&H Circular dated 06.10.2021, for a period of up to one month from the date of this Order.”

23. It is also relevant to note para 5 of the MoRTH circular, which is extracted hereunder: “5. Before deciding a contractor/concessionaire as Non Performer debarring/penalizing it, the concerned authority shall issue a notice to the contractor/concessionaire by giving 15 days' time to furnish its written reply and allow personal hearing, if so desired by the contractor/concessionaire, before the competent authority or any person designated for the purpose. Such a notice shall not be issued without the approval of an officer below the rank of Chief Engineer/CGM/ED. In case of projects where public safety is endangered by the behavior/conduct/action of the consultant/contractor/concessionaire, the authority may temporarily suspend the consultant/contractor/concessionaire from participating in ongoing/ future bidding upto 1 month period during which the regular process of debarment shall be concluded.”

24. A bare reading of the para 5, prima facie, demonstrates that before the authority can proceed against any contractor or concessionaire as a non-performer or initiate any action for debarring or penalizing it, the authority is required to issue a notice to the entity by giving a 15 days’ time to furnish its written reply and allow personal hearing, if so desired by the said

contractor/concessionaire. This, itself, appears to be a provision ensuring compliance of Principles of Natural Justice before any administrative action is taken by the authority. The power to temporarily suspend the contractor/concessionaire from participating in ongoing and future bidding upto one month period is also provided in para 5, however, it does not appear at this stage, prima facie, that this portion of para 5 is an exception or delinked from the previous portion which required giving a 15 day prior notice before proceeding to take any action in respect of declaring the contractor/concessionaire as an non-performer or initiation of action for debarring it.

25. That apart, learned senior counsel has also invited attention of this Court to the CSIR-CRRI Report, which was generated at the instance of the competent authority, pursuant to the direction of the learned Division Bench of the High Court of Tripura, which was submitted to it in the month of September, 2026. This Court has perused the relevant pages and paragraphs as indicated by the learned senior counsel, which are extracted hereunder for the purpose of clarity:

26. From a perusal of the aforesaid paragraphs, it appears that the CSIR-CRRI Report, which is an independent authority and has submitted its report, prima facie, appears to be indicating that the work executed by the petitioner in respect of the payment etc., are either fair or good and definitely does not appear to indicate any adverse report of the status and condition of the project stretch which was contracted to the petitioner.

27. In that view of the matter and having regard to the fact that the respondent is yet to demonstrate, if any notice, as contemplated under para 5 of the MoRTH Circular dated 06.10.2021 was issued, it appears justifiable and in the interest of justice to keep the impugned order dated 25.09.2026 of temporary suspension, in abeyance till the next date of listing.

28. At this stage, learned counsel for the respondent states, under instructions, that the parties may be referred to arbitration.

29. Mr. Jayant Mehta, learned senior counsel, under instructions of learned counsel for the petitioner, agrees to the same.

30. Though, it is noted that Clause 26.1 regarding dispute resolution also contemplates conciliation proceedings to proceed the arbitration, however, the parties are ad idem that the disputes be referred to arbitration straightaway by this Court.

31. The parties are also ad idem that irrespective of what the arbitration clause envisages regarding the constitution of the Tribunal, they are agreeable that the said arbitration be conducted by a Sole Arbitration, preferably, retired Judge of the High Court under the aegis of the Delhi International Arbitration Centre (hereinafter referred to as ‘DIAC’).

32. If that be so, this Court appoints Mr. Justice G.S. Sistani (Retd.), (Mobile: 9871300034), as the learned Arbitrator who shall adjudicate the disputes between the parties under the Rules framed by the DIAC.

33. The fees of the learned Arbitrator shall be in terms of DIAC (Administrative Cost and Arbitrators’ Fees) Rules, 2018. Learned Arbitrator is requested to submit the requisite declaration under Section 12 of the Act.

34. The petitioner shall approach the learned Arbitrator within two weeks from today.

35. The learned Tribunal shall treat the present petition under Section 9 as well under Section 17 of the Act and proceed to dispose it of without being influenced by the observations made herein.

36. Needless to state that the present order shall operate till the Tribunal considers and disposes of the present application.

37. Dasti under the signatures of Court Master.

TUSHAR RAO GEDELA, J OCTOBER 1, 2026/anj

You have used today's free searches. Sign in, for free, to keep searching without a limit.

Compass reads the judgments for you and finds the paragraphs for and against your question. Sign in to use it.

My Vault follows judgments for you and records every later decision that cites them. Sign in to keep one.

Sign in to download the court's PDF. The full text stays free to read here.

Sign in, for free, to download the court copy. Reading the full text here stays open to everyone.

Search and read Indian judgments without limits, save them to My Vault and find the relevant paragraphs with Compass.

Open the sign-in page instead