Delhi High Court

ARB.P./1452/2026 of GSBA BUILDERS PVT LTD Vs DELHI DEVELOPMENT AUTHORITY on 18 August 2026

Cites 4, Cited by 0

Page 1 of 6 $~54 * IN THE HIGH COURT OF DELHI AT NEW DELHI # CNR No. DLHC010381372026 + ARB.P. 1452/2026 GSBA BUILDERS PVT LTD .....Petitioner Through: Mr. J. Sai Deepak, Sr. Adv. alongwith Mr. Ravi Kapoor, Mr. Rishav and Ms. Aditi Singhal, Advocates. versus DELHI DEVELOPMENT AUTHORITY

ARB.P. 1452/2026

$~54

*

IN THE HIGH COURT OF DELHI AT NEW DELHI

CNR No. DLHC010381372026

+

ARB.P. 1452/2026

GSBA BUILDERS PVT LTD

.....Petitioner

Through:

Mr. J. Sai Deepak, Sr. Adv. alongwith

Mr. Ravi Kapoor, Mr. Rishav and Ms.

Aditi Singhal, Advocates.

versus

DELHI DEVELOPMENT AUTHORITY

.....Respondent

Through:

Mr. Ramesh Singh, Sr. Adv. alongwith

Ms. Prabhsahay Kuar, SC for DDA

alongwith Mr. Aditya Verma, Mr.

Siddhant M, Advocates And Mr. Durga

Prasad (AE, DDA)

CORAM:

HON'BLE MR. JUSTICE SACHIN DATTA

%

18.08.2026

Citations and Judicial Treatment

No citing decisions in the index yet

Cited by

0

Decisions in the index citing it

Cites

4

Decisions referred to

In this index

3

Of the decisions it cites

Overruled / Questioned

0

No negative treatment found

Loading the citing and cited decisions…

O R D E R

1. The present petition has been filed by the petitioner seeking appointment of a sole Arbitrator for adjudication of the disputes and claims arising in connection with an agreement dated 10.06.2020 read with Letter of Acceptance dated 04.05.2020.

2. The aforesaid agreement was in the context of construction work of a Multi-Level Car Parking (MLCP) at Modi Tower, Nehru Place, New Delhi, including all development works and services on EPC (Engineering, Procurement, and Construction) basis, including two years of Operation and Maintenance, by the respondent.

3. It is the case of the petitioner that during the execution of the construction phase, the project was impacted by various hindrances and factors that were beyond the control of the petitioner, resulting in provisional extension of the completion deadline.

4. It is submitted by the petitioner that despite these impediments, the This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 21/08/2026 at 11:26:16

ARB.P. 1452/2026

petitioner successfully completed the construction work to the complete satisfaction of the respondent which was officially acknowledged vide issuance of completion certificate on 12.02.2026.

5. The petitioner is aggrieved by the fact that despite full completion of the project and issuance of completion certificate, the respondent arbitrarily sought to impose liquidated damages and also sought to encash certain bank guarantees submitted by the petitioner.

6. A petition under Section 9 of the Arbitration & Conciliation Act, 1996 has also been filed by the petitioner with regard to the invocation of the said bank guarantees.

7. The arbitration clause (clause 25 of the General Condition of Contract) in the contract between the parties is in the following terms: Clause 25

This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 21/08/2026 at 11:26:16

ARB.P. 1452/2026

This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 21/08/2026 at 11:26:16

ARB.P. 1452/2026

This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 21/08/2026 at 11:26:16

ARB.P. 1452/2026

8. Issue notice.

9. Learned counsel, as aforesaid, accepts notice on behalf of the respondent.

10. Learned senior counsel for the respondent while vehemently disputing the contentions sought to be raised by the petitioner on the merits of the dispute, accedes to the existence of the arbitration agreement and to this Court appointing an independent Sole Arbitrator to adjudicate the dispute between the parties.

11. He further submits that the respondent is desirous of raising certain counter-claims against the petitioner on account of alleged breaches on the part of the petitioner.

12. Since the existence of the arbitration clause is evident from a bare perusal of the contract, there is no impediment to constituting an arbitral tribunal for adjudicating the dispute between the parties, as mandated in terms of the judgments of Supreme Court in SBI General Insurance Co. Ltd. v. Krish Spinning, (2024) 12 SCC 1 and Interplay Between Arbitration Agreements under Arbitration Act, 1996 & Stamp Act, 1899, In re, (2024) 6 SCC 1. The said legal position has also been subsequently reiterated and followed by the Supreme Court in Aslam Ismail Khan Deshmukh v. ASAP Fluids Private Limited & Anr., (2025) 1 SCC 502 and Maharashtra State This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 21/08/2026 at 11:26:16

ARB.P. 1452/2026

Electricity Distribution Co. Ltd. & Ors. v. R Z Malpani, 2026 SCC OnLine SC 553.

13. Considering the circumstances, with the consent of the parties, Ms. Justice (Retd.) Rekha Palli, former Judge, Delhi High Court is appointed as the Sole Arbitrator to adjudicate the dispute between the parties.

14. The learned Sole Arbitrator may proceed with the arbitration proceedings subject to furnishing requisite disclosures to the parties as required under Section 12 of the A&C Act.

15. The learned Sole Arbitrator shall be entitled to fee in accordance with IV th

16. All rights and contentions of the parties in relation to the claims/ counter-claims are kept open, to be decided by the learned Arbitrator on their merits, in accordance with law. Schedule to the A&C Act; or as may otherwise be agreed to between the parties and the learned Sole Arbitrator.

17. Needless to say, the learned Sole Arbitrator would consider the same in accordance with law and take an appropriate decision.

18. The respondent shall be entitled to raise preliminary objections as regards jurisdiction/ arbitrability, which shall be decided by the learned arbitrator, in accordance with law.

19. Needless to say, nothing in this order shall be construed as an expression of this Court on the merits of the case.

20. The petitioner requests that the learned Sole Arbitrator be requested to schedule a date of hearing expeditiously. The petitioner would be at liberty to make a request in this regard to the learned Sole Arbitrator.

21. The petition stands disposed of in the above terms. SACHIN DATTA, J AUGUST 18, 2026/at/nb This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 21/08/2026 at 11:26:16

You have used today's free searches. Sign in, for free, to keep searching without a limit.

Compass reads the judgments for you and finds the paragraphs for and against your question. Sign in to use it.

My Vault follows judgments for you and records every later decision that cites them. Sign in to keep one.

Sign in to download the court's PDF. The full text stays free to read here.

Sign in, for free, to download the court copy. Reading the full text here stays open to everyone.

Search and read Indian judgments without limits, save them to My Vault and find the relevant paragraphs with Compass.

Open the sign-in page instead