Delhi High Court

CONT.CAS(C)/1414/2026 of NKG INFRASTRUCTURE LTD Vs MR. AKHILESH MISHRA on 7 August 2026

Cites 0, Cited by 0

$~56 * IN THE HIGH COURT OF DELHI AT NEW DELHI # CNR No. DLHC010362652026 + CONT.CAS(C) 1414/2026 & CM APPL. 52181/2026 NKG INFRASTRUCTURE LTD. .....Petitioner Through: Mr. Stephin George and Mr. Divyansh Jain, Advs. Mob: 7769852182 versus MR. AKHILESH MISHRA .....Respondent Through: Ms.

$~56

*

IN THE HIGH COURT OF DELHI AT NEW DELHI

#

CNR No. DLHC010362652026

+

CONT.CAS(C) 1414/2026 & CM APPL. 52181/2026

NKG INFRASTRUCTURE LTD.

.....Petitioner

Through:

Mr.

Stephin

George

and

Mr.

Divyansh Jain, Advs.

Mob: 7769852182

versus

MR. AKHILESH MISHRA

.....Respondent

Through:

Ms. Aastha Gupta, SPC with Ms.

Sapna and Ms. Arzoo Khan, Advs.

Mob: 9971103104

Email: aastha.advocate@gmail.com

CORAM:

HON'BLE MS. JUSTICE MINI PUSHKARNA

Citations and Judicial Treatment

No citing decisions in the index yet

Cited by

0

Decisions in the index citing it

Cites

0

Decisions referred to

In this index

0

Of the decisions it cites

Overruled / Questioned

0

No negative treatment found

Loading the citing and cited decisions…

O R D E R

% 07.08.2026

1. The present petition has been filed alleging wilful disobedience of the order dated 10th April, 2026, passed by this Court in W.P.(C) 4748/2026, wherein, it had been directed that the representation of the petitioner be decided by the Public Works Department (“PWD”), within a period of three months, from the date of receipt of such representation.

2. Since the aforesaid order has not been complied with, the present contempt petition has come to be filed.

3. Issue notice. Notice is accepted by learned counsel appearing for the respondent.

4. Learned counsel appearing for the respondent submits that the This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 11/08/2026 at 11:17:46

respondent-Executive Engineer (Electrical), PWD, has recently joined the said posting.

5. She submits on instructions that the representation of the petitioner shall be decided, within a period of four weeks from today.

6. The aforesaid statement made by learned counsel appearing for the respondent is taken note of, and the respondent is held bound by the same.

7. Accordingly, no further order is required to be passed in the present petition.

8. However, in case, the petitioner is aggrieved by any non-action on the part of the respondent, the petitioner shall be at liberty to revive the present petition.

9. Noting the aforesaid, the present petition is accordingly disposed of.

10. The pending application also stands disposed of. MINI PUSHKARNA, J AUGUST 7, 2026/SK This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 11/08/2026 at 11:17:46

You have used today's free searches. Sign in, for free, to keep searching without a limit.

Compass reads the judgments for you and finds the paragraphs for and against your question. Sign in to use it.

My Vault follows judgments for you and records every later decision that cites them. Sign in to keep one.

Sign in to download the court's PDF. The full text stays free to read here.

Sign in, for free, to download the court copy. Reading the full text here stays open to everyone.

Search and read Indian judgments without limits, save them to My Vault and find the relevant paragraphs with Compass.

Open the sign-in page instead