Delhi High Court

W.P.(C)/4561/2024 of RAMESH Vs GOVT. OF NCT OF DELHI & ANR. on 4 May 2026

Cites 0, Cited by 0

HIGH COURT OF DELHI AT NEW DELHI + W.P.(C) 4561/2024 RAMESH .....Petitioner Through: Mr. Charanjit Sharma and Ms. Mata Sharma, Advs. versus GOVT. OF NCT OF DELHI & ANR. .....Respondents Through: Mr. Sanjay Kumar Pathak, SC, with Mr. Sunil Kumar Jha, Mr. M. S. Akhtar, Mr. Kushagra Dixit, Ms.

$~32

*

IN THE HIGH COURT OF DELHI AT NEW DELHI

+

W.P.(C) 4561/2024

RAMESH

.....Petitioner

Through:

Mr. Charanjit Sharma and Ms. Mata

Sharma, Advs.

versus

GOVT. OF NCT OF DELHI & ANR.

.....Respondents

Through:

Mr. Sanjay Kumar Pathak, SC, with

Mr. Sunil Kumar Jha, Mr. M. S.

Akhtar, Mr. Kushagra Dixit, Ms.

Joohu Kumari, Advs.

CORAM:

JUSTICE PRATHIBA M. SINGH

JUSTICE MADHU JAIN

Citations and Judicial Treatment

No citing decisions in the index yet

Cited by

0

Decisions in the index citing it

Cites

0

Decisions referred to

In this index

0

Of the decisions it cites

Overruled / Questioned

0

No negative treatment found

Loading the citing and cited decisions…

O R D E R

% 04.05.2026

1. This hearing has been done through hybrid mode.

2. The present petition has been filed by the Petitioner under Article 226 of the Constitution of India, inter alia, seeking release of the amount of compensation in respect of the land in question being Khasra No. 58//16min(1-11) & 25min((1-4) situated at the revenue estate of Village Pooth Khurd, Delhi.

3. On 9th September, 2009, a notification was issued qua the land of the Petitioner under Section 4 of the Land Acquisition Act, 1894. The award being Award No.02/2012-13 has also been passed on 5th September, 2012. However, compensation has not been released to the Petitioner till date. Hence, the present petition.

4. It is clear from the facts that a substantial period has already lapsed and This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 08/05/2026 at 12:11:32

the amount is liable to be paid to the Petitioner. The only reason given by the LAC is insufficiency of funds.

5. In the opinion of this Court, the same is not a sufficient ground to not pay the compensation to the Petitioner. Accordingly, let the compensation be released to the Petitioner within a period of four months from now.

6. The petition along with pending applications, if any, is disposed of in above terms.

7. List for compliance on 29th September, 2026. PRATHIBA M. SINGH, J. MADHU JAIN, J. MAY 4, 2026/prg/ck This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 08/05/2026 at 12:11:32

You have used today's free searches. Sign in, for free, to keep searching without a limit.

Compass reads the judgments for you and finds the paragraphs for and against your question. Sign in to use it.

My Vault follows judgments for you and records every later decision that cites them. Sign in to keep one.

Sign in to download the court's PDF. The full text stays free to read here.

Sign in, for free, to download the court copy. Reading the full text here stays open to everyone.

Search and read Indian judgments without limits, save them to My Vault and find the relevant paragraphs with Compass.

Open the sign-in page instead