Gauhati High Court

FAO/3/2026 of Sh. P.C. Lalrinawma Vs State of Mizoram r/b the Chief Secretary to the Govt of Mizoram and 6 Ors. on 1 July 2026

Cites 0, Cited by 0

GAHC030004382026 THE GAUHATI

GAHC030004382026

THE GAUHATI HIGH COURT

(HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)

Case No. : FAO/3/2026

Sh. P.C. Lalrinawma

S/o Sawikunga (L)

R/o Dinthar Veng, Aizawl

Mizoram

VERSUS

State of Mizoram r/b the Chief Secretary to the Govt of Mizoram and 6 Ors.

Aizawl

2:The Secretary to the Govt of Mizoram

Land Revenue and Settlement Deptt

Govt of Mizoram

3:The Director

Land Revenue and Settlement Deptt. Govt of Mizoram 4:The Settlement Officer Land Revenue and Settlement Deptt Govt of Mizoram 5:The Commissioner Aizawl Municipal Council 6:Smt Ralmanthangi 7:Sh H. Lalnunmawia (L

Advocate for the Petitioner : Mr. Lalrokunga Pautu

Advocate for the Respondent :

BEFORE

HONOURABLE MR. JUSTICE RAJESH MAZUMDAR

Citations and Judicial Treatment

No citing decisions in the index yet

Cited by

0

Decisions in the index citing it

Cites

0

Decisions referred to

In this index

0

Of the decisions it cites

Overruled / Questioned

0

No negative treatment found

Loading the citing and cited decisions…

ORDER

Date : 02-07-2026 Heard Mr. Lalrokunga Pautu, learned counsel appearing for the appellant.

2. This appeal is against the Order dated 17.04.2026 passed by the learned Civil Judge (Senior Division)-II in CMA No. 759/2025 A/o Civil Suit No. 106/2025.

3. By the impugned order, the learned Trial Court had required a verification to be conducted by the defendant Nos. 1 to 4 and defendant No. 5 in respect of their jurisdiction and to submit a report on 18.05.2026. By the same order, the defendant No. 6 was allowed to continue her construction on the eastern portion of the building.

4. The learned counsel for the appellant has submitted that pursuant to the aforesaid order, the spot verification had already been carried out and a report dated 22.05.2026 had been prepared and a copy of the same has also been obtained by the appellants from the Officer-in-charge of the Vaivakawn Police Station and which is annexed to the appeal at page-171. It is seen that the directions for carrying out a spot verification by the defendant Nos. 1 to 4 and defendant No. 5 has already been carried out and the same will naturally be taken into consideration by the learned Trial Court as and when it is placed before the said Court and necessary orders would be passed in the litigation pending before it.

5. The learned counsel for the appellant has however submitted that allowing the defendant No. 6 to continue her construction on any portion of the building, let alone the eastern portion of the building, would cause serious prejudice to the appellant and as would be evident from the report dated 22.05.2026, the defendant No. 6 in the litigation before the learned Trial Court has continued construction work of the RCC building over the entire disputed area. In such circumstances, he has submitted that the Order dated 17.04.2026 deserves an interference.

6. The matter is pending adjudication before the learned Trial Court and relevant documents have been placed on record before the learned Trial Court. An appropriate application, stated to be numbered as CMA No. 485/2026, has also been filed, on which by the Order dated 18.06.2026, the learned Trial Court had recorded that the written objections have been received and the Court was adjourned fixing 30.07.2026. In view of the circumstances involved in this FAO, we do not deem it fit to keep the appeal pending before this Court and we also deem it fit that the learned Trial Court is required to adjudicate the litigation pending before it expeditiously.

7. Accordingly, this FAO is disposed of modifying the Order dated 17.04.2026 to the extent that the permission granted to the defendant No. 6 to continue her construction on the building in the disputed area within LSC No. 408/1974 is set aside and quashed. The defendant No. 6 shall not carry on any further construction on the building till 30.07.2026. The learned Trial Court shall on 30.07.2026, on an appropriate application being filed by the appellant for restraining the defendant No. 6 further on, adjudicate the same application as expeditiously as possible.

8. The FAO is accordingly disposed of.

9. The learned Trial Court shall be at liberty to proceed with the adjudication of the Civil Suit No. 106/2025 and other miscellaneous applications arising therein in accordance with law.

JUDGE Comparing Assistant

You have used today's free searches. Sign in, for free, to keep searching without a limit.

Compass reads the judgments for you and finds the paragraphs for and against your question. Sign in to use it.

My Vault follows judgments for you and records every later decision that cites them. Sign in to keep one.

Sign in to download the court's PDF. The full text stays free to read here.

Sign in, for free, to download the court copy. Reading the full text here stays open to everyone.

Search and read Indian judgments without limits, save them to My Vault and find the relevant paragraphs with Compass.

Open the sign-in page instead