Jammu and Kashmir High Court

WP(C)/3170/2026 of JAVAID IQBAL Vs UT OF J AND K TH. COMMISSIONER SECRETARY, RURAL DEVELOPMENT DEPARTMENT, JAMMU AND OTHERS on 5 October 2026

OF JAMMU & KASHMIR AND LADAKH AT JAMMU WP (C) No. 3170/2026 CM No. 7002/2026 Javaid Iqbal …..Petitioner(s) Through: Mr. Tariq Mugal, Advocate Vs UT of J&K and others .…. Respondent(s) Through: Mr. Raman Sharma, AAG with Ms. Saliqa Sheikh, Advocate Coram: HON’BLE MR.

HIGH COURT OF JAMMU & KASHMIR AND LADAKH

AT JAMMU

WP (C) No. 3170/2026

CM No. 7002/2026

Javaid Iqbal

…..Petitioner(s)

Through: Mr. Tariq Mugal, Advocate

Vs

UT of J&K and others

.…. Respondent(s)

Through: Mr. Raman Sharma, AAG with

Ms. Saliqa Sheikh, Advocate

Coram: HON’BLE MR. JUSTICE SHAHZAD AZEEM, JUDGE

ORDER

05.10.2026

1. The petitioner has invoked the extraordinary jurisdiction of this Court under the Article 226 of the Constitution of India seeking quashing of order dated 18.07.2026, passed by respondent No. 5, Executive Engineer, Rural Engineering Wing, Doda, whereby, the Competent Authority has decided to debar the petitioner from participating in any tendering process/work execution under this Department for a period of one year with immediate effect and also forfeiting of CDR in accordance with applicable rules and regulations.

2. The facts in brief are that vide allotment order dated 06.08.2025, the petitioner was allotted the construction work of CSC at Khan Mohalla, Ward No. 01, Panchayat Sanwara, Block Chilly Pingal, Doda. However, he was required to execute the work within a stipulated time but due to alleged dispute in respect of land over which the construction has to be carried out, the requisite work could not be completed within stipulated period, which led to the passing of the impugned order. Sr. No. 17

2 WP (C) No. 3170/2026

Page 1 of 2

3. At this stage, Mr. Raman Sharma, learned AAG has taken a preliminary objection with regard to maintainability of the writ petition on the ground that the allotment order itself contains an Arbitration Clause and in this view of the matter once efficacious and alternative remedy available to the petitioner, this petition is not maintainable.

4. There is no quarrel to the settled proposition of law that once in a contractual dispute there is an Arbitration Clause, the parties are required to resort to the alternate remedy of the Arbitration and the writ is not the efficacious remedy.

5. However, keeping in view the nature of controversy involved, this writ petition is entertained for the limited purpose that despite the petitioner has responded to the impugned order but till date no action has been taken so far.

6. Therefore, this writ petition is taken on board and disposed of with the direction to the respondents to consider the representation dated 02.09.2026 and proceed in the matter in accordance with law and in case the grievance of the petitioner still remained un-redressed, he shall be at liberty to take recourse to the arbitration clause in terms of the allotment order dated 06.08.2025. Let this exercise be completed within a period of four weeks, from the date a certified copy of this order is made available.

7. Disposed of.

(Shahzad Azeem) Judge Jammu 05.10.2026 Mahavir

Page 2 of 2

Loading citations and judicial treatment…

You have used today's free searches. Sign in, for free, to keep searching without a limit.

Compass reads the judgments for you and finds the paragraphs for and against your question. Sign in to use it.

My Vault follows judgments for you and records every later decision that cites them. Sign in to keep one.

Sign in to download the court's PDF. The full text stays free to read here.

Search and read Indian judgments without limits, save them to My Vault and find the relevant paragraphs with Compass.

Open the sign-in page instead