Jammu and Kashmir High Court
Arb P/106/2026 of M/S LAKHANPAL FABRICATORS TH. RAGHUNATH LAKHANPAL Vs UNION OF INDIA , BORDER ROADS ORGANISATION TH. ITS DIRECTOR GENERAL,NEW DELHI AN DOTHERS on 25 September 2026
g e Serial No.01 REGULAR CAUSE LIST HIGH COURT OF JAMMU & KASHMIR AND LADAKH AT JAMMU (Through Virtual Mode) Arb P 106/2026 M/S LAKHANPAL FABRICATORS TH. RAGHUNATH LAKHANPAL …Petitioner(s) Through: Ms. Deepali Arora, Advocate. Vs. UNION OF INDIA, BORDER ROADS ORGANISATION TH. ITS
1 | P a g e
Serial No.01
REGULAR CAUSE LIST
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT JAMMU
(Through Virtual Mode)
Arb P 106/2026
M/S LAKHANPAL FABRICATORS
TH. RAGHUNATH LAKHANPAL
…Petitioner(s)
Through:
Ms. Deepali Arora, Advocate.
Vs.
UNION OF INDIA, BORDER ROADS
ORGANISATION TH. ITS DIRECTOR
GENERAL, NEW DELHI AN
DOTHERS
...Respondent(s)
Through:
Mr. Vishal Sharm, DSGI with
Mr. Karan Sharma, CGSC.
CORAM:
HON’BLE MR. JUSTICE SANJAY PARIHAR, JUDGE
Citations and Judicial Treatment
Cited by
0
Decisions in the index citing it
Cites
0
Decisions referred to
In this index
0
Of the decisions it cites
Overruled / Questioned
0
No negative treatment found
Loading the citing and cited decisions…
This judgment in the centre: on the left the decisions it cites, on the right the decisions citing it. Colour is the treatment; choose a decision to open it.
ORDER
25.09.2026
1. Ld. DSGI, Mr. Vishal Sharma, fairly submits that he has no objection to the application preferred by the petitioner seeking extension of the mandate of the Arbitral Tribunal.
2. In view of the aforesaid submission made by the ld. DSGI, and for the reasons stated in the application, the application is allowed. Accordingly, the mandate of the Arbitral Tribunal constituted in Arbitration Petition No. 58/2023, vide order dated 20th December, 2024, in relation to Work Order No. 800715/23/E8 for the design and construction of a 50-metre span steel superstructure, through-type major permanent bridge on open foundation over Poonch Nallah at Km 97.70 on the Srinagar–Baramulla–Uri road, under Project Beacon in the Union Territory of Jammu and Kashmir, pursuant to Contract
2 | P a g e
Agreement No. CA No. CE(P)BCN/08/2007/08, is hereby extended for a further period of three months from the date of expiry of the previous term.
3. The Arbitral Tribunal is expected to conclude the arbitral proceedings within the aforesaid extended period, in accordance with law.
4. A copy of this order shall be made available to the ld. Counsel for the parties under the name and signature of the Secretary.
5. The application stands disposed of accordingly. (Sanjay Parihar)
Judge
SRINAGAR: 25.09.2026 Shaista-PS