Jammu and Kashmir High Court

CPOWP/127/2018 of M/S SHIVAM ENGINEERING WORKS Vs M.RAJU SECY.P.H.E.DEPTT. on 14 August 2026

Cites 0, Cited by 0

OF JAMMU & KASHMIR AND LADAKH AT JAMMU CPOWP No. 127/2018 M/s Shivam Engineering Works …..Appellant(s)/Petitioner(s) Through: Ms. Rozina Afzal, Sr. Advocate with Ms. Ishrat Bukhari, Advocate vs M. Raju Secy. P.H.E. Deptt. .…. Respondent(s) Through: Ms. Monika Kohli, Sr. AAG

HIGH COURT OF JAMMU & KASHMIR AND LADAKH

AT JAMMU

CPOWP No. 127/2018

M/s Shivam Engineering Works

…..Appellant(s)/Petitioner(s)

Through: Ms. Rozina Afzal, Sr. Advocate with Ms. Ishrat Bukhari, Advocate

vs

M. Raju Secy. P.H.E. Deptt.

.…. Respondent(s)

Through: Ms. Monika Kohli, Sr. AAG with

Ms. Sagira Jaffar, Advocate

Coram: HON’BLE MR. JUSTICE RAJNESH OSWAL, JUDGE

Citations and Judicial Treatment

No citing decisions in the index yet

Cited by

0

Decisions in the index citing it

Cites

0

Decisions referred to

In this index

0

Of the decisions it cites

Overruled / Questioned

0

No negative treatment found

Loading the citing and cited decisions…

ORDER

14.08.2026

1. In the earlier status report filed by the respondents, it was stated that the petitioner firm had not submitted all the requisite bills/claims with the respondents. In the subsequent status report filed by the respondents, it is stated that the office has examined the photocopies of the bills submitted by the petitioner and upon such examination, it was found that the bills submitted by the petitioner were not verified by any official of the department and moreover the same were not found entered in the Measurement Book maintained by the concerned Junior Engineer/Assistant Executive Engineer. Further, from the available records in the divisional office, it cannot be ascertained that the works have been executed. This shows that the bills are not genuine as per the record available. Therefore, the payment cannot be made to the petitioner as claimed by him.

2. In terms of order dated 21.02.2018, the writ petition was disposed with a direction to respondent No. 3 to release the amount outstanding for the work executed by the petitioner-firm for repair of the centrifugal Serial No. 39

2 CPOWP No. 127/2018

pumps/submersible pumps of the department of the respondents. Simultaneously, the writ Court had observed that the Court had not expressed any opinion on the merits of the claim of the petitioner.

3. In view of the status report filed by the respondents, there is serious dispute with regard to the documents, made basis for claiming the amount from the respondents.

4. In view of the above, the proceedings in the present contempt petition are closed with liberty to the petitioner to avail an appropriate remedy as available under law.

5. Disposed of.

(RAJNESH OSWAL)

JUDGE

Jammu 14.08.2026 Neha-II NEHA KUMARI 2026.08.14 16:31 I attest to the accuracy and integrity of this document

You have used today's free searches. Sign in, for free, to keep searching without a limit.

Compass reads the judgments for you and finds the paragraphs for and against your question. Sign in to use it.

My Vault follows judgments for you and records every later decision that cites them. Sign in to keep one.

Sign in to download the court's PDF. The full text stays free to read here.

Sign in, for free, to download the court copy. Reading the full text here stays open to everyone.

Search and read Indian judgments without limits, save them to My Vault and find the relevant paragraphs with Compass.

Open the sign-in page instead