OF JAMMU & KASHMIR AND LADAKH AT JAMMU AA No. 1/2025 M/S D S Constructions, Govt. Approved and Registered “ A ” Class Builders and Contractors 128, Cantt. Road, Garha, Jalandhar, Through its partner Sh. Diljeet Singh Sachdeva, Age 36 years, S/o Sh. Jasvinder Singh R/o 848,

HIGH COURT OF JAMMU & KASHMIR AND LADAKH

AT JAMMU

AA No. 1/2025

M/S D S Constructions,

Govt. Approved and Registered

“A” Class Builders and Contractors 128,

Cantt. Road, Garha, Jalandhar,

Through its partner Sh. Diljeet Singh Sachdeva, Age 36 years, S/o Sh. Jasvinder Singh R/o 848, Urban Estate, Phase-II, Jalandhar (Pb.)

….. Petitioner

Through: Mr. Jugal Kishore Gupta, Advocate

Vs

1.

Union of India, Through Secretary to Govt.

Ministry of Defence,

South Block, New Delhi.

2.

The Chief Engineer,

HQ CE (AF) Udhampur Zone,

Air Force Station, Udhampur,

PIN-182101 (J&K)

3.

HQ Commander Works Engineer,

Air Force, Leh

PIN-900465 C/o 56 APO

4.

Garrison Engineer (AF) Thoise

Military Engineering Services,

PIN-937219 C/o 56 APO

.….Respondents

Through: Mr. Vishal Sharma, DSGI with

Mr. Eishaan Dadhichi, CGSC

CORAM:

HON’BLE MR. JUSTICE M A CHOWDHARY, JUDGE

Citations and Judicial Treatment

No citing decisions in the index yet

Cited by

0

Decisions in the index citing it

Cites

0

Decisions referred to

In this index

0

Of the decisions it cites

Overruled / Questioned

0

No negative treatment found

Loading the citing and cited decisions…

ORDER

(14.07.2026)

01. Petitioner, through the medium of this petition filed under section 9 of the Arbitration and Conciliation Act, 1996, is aggrieved of the impugned Supplementary List-1 Serial No. 94

2

AA No. 1/2025

Order/Letter No. 85021/CEAFU12/253/E8 dated 13.02.2025 issued by the respondent No. 2 – Chief Engineer to the extent of cancellation of contract work under condition 54 of the General condition of Contract (IAFW-2249), which provides that the balance work shall be completed through another agency, at the risk and cost of the contractor.

02. Learned counsel for the parties submit that Mr. Satish Chandra, Additional Director General (Retd.), has been appointed as a sole arbitrator, to arbitrate the disputes arising out of the contract between the parties vide order dated 11.02.2026, passed by this Court in Arbitration Petition No. 54/2025.

03. Learned counsel for the petitioner submits that the interim arrangement ordered by this Court on 18.03.2025 be made subject to the outcome of the arbitration proceedings. Learned counsel for the respondents has stated no objections to this plea.

04. Accordingly, this petition is disposed of, at this stage, providing that the interim order dated 18.03.2025 passed in this petition and the recovery, if any, which was stayed by this Court vide interim order dated 26.11.2025 shall be subject to the outcome of arbitration proceedings.

05. The petition is disposed of, accordingly.

(M A CHOWDHARY) JUDGE JAMMU

14.07.2026

Shivalee

Shivalee Khajuria 2026.07.15 14:11 I attest to the accuracy and integrity of this document

You have used today's free searches. Sign in, for free, to keep searching without a limit.

Compass reads the judgments for you and finds the paragraphs for and against your question. Sign in to use it.

My Vault follows judgments for you and records every later decision that cites them. Sign in to keep one.

Sign in to download the court's PDF. The full text stays free to read here.

Sign in, for free, to download the court copy. Reading the full text here stays open to everyone.

Search and read Indian judgments without limits, save them to My Vault and find the relevant paragraphs with Compass.

Open the sign-in page instead