Jammu and Kashmir High Court

WP(C)/781/2026 of AMIR FAROOQ BHATT Vs UT OF J AND K TH COMMISSIONER SECRETARY TO GOVERNMENT RURAL DEVELOPMENT DEPARTMENT, JAMMU AND OTHERS on 1 April 2026

Cites 0, Cited by 0

OF JAMMU & KASHMIR AND LADAKH AT JAMMU WP(C) No. 781/2026 CM No. 1769/2026 Amir Farooq Bhatt S/O Mohd. Farooq Bhat R/O Rajnagar, Lower Ghabar, Tehsil Budhal District Rajouri. …..Appellant(s)/Petitioner(s) Through: Mr. Mohd. Arif, Adv. 1. Union Territory of Jammu and Kashmir Through

HIGH COURT OF JAMMU & KASHMIR AND LADAKH

AT JAMMU

WP(C) No. 781/2026

CM No. 1769/2026

Amir Farooq Bhatt

S/O Mohd. Farooq Bhat

R/O Rajnagar, Lower Ghabar,

Tehsil Budhal District Rajouri.

…..Appellant(s)/Petitioner(s)

Through: Mr. Mohd. Arif, Adv.

1. Union Territory of Jammu and Kashmir

Through Commissioner/Secretary, Rural

Development Department, Civil Secretariat, Jammu/Srinagar.

2. District Development Commissioner, Rajouri.

3. Assistant Commissioner, Development Rajouri.

4. Executive Engineer REW, Rajouri.

5. Block Development Officer, (BDO), Rajouri.

.…. Respondent(s)

Through: Ms. Jagmeet Kour, Adv. vice

Mr. Raman Sharma, AAG

CORAM: HON’BLE MR. JUSTICE M A CHOWDHARY, JUDGE

Citations and Judicial Treatment

No citing decisions in the index yet

Cited by

0

Decisions in the index citing it

Cites

0

Decisions referred to

In this index

0

Of the decisions it cites

Overruled / Questioned

0

No negative treatment found

Loading the citing and cited decisions…

ORDER

(01.04.2026)

1. The petitioner, through the medium of this petition, seeks direction to the respondents to accord sanction for release of an amount of Rs. 17.31 lakhs and also to release and pay the same to the petitioner within a time frame, along with interest @ 7.5 % from the date the same fell due till its realization.

2. Learned counsel for the petitioner submits that the petitioner having been allotted a work for construction of ‘One Stop Centre for women’ at Rajouri under the Scheme known as BADP Tribal during the year, 2018-19 vide communication No. XEN/REW/2020-21/90 dated 23.06.2020 with an Serial No. 122

2 WP(C) No. 781/2026

estimated cost of Rs. 62.42 lakhs and that an amount of Rs. 45.11 lakhs has been paid to the petitioner whereas, balance amount of Rs. 17.31 lakhs is pending as liability despite completion of work as certified by the Executive Engineer, REW Rajouri vide No. XEN/REW/2020-21/90 dated 23.06.2020.

3. Learned counsel for the petitioner submits that the petitioner shall be satisfied in case the petition is disposed of with a direction to the respondents to treat this petition as representation and decide the same expeditiously with regard to the claim raised by the petitioner in this petition.

4. Learned counsel for the respondents states no objection to the submissions made for disposal of the petition to decide the petitioner’s claim in accordance with law.

5. In view of the submissions urged at the bar and no objection from the other side, the petition is disposed of with a direction to the respondents to treat the petition as representation and decide the same within a period of four weeks, from the date, a certified copy of this order is made available to them.

6. Disposed of along with connected application(s).

(M A CHOWDHARY)

JUDGE Jammu 01.04.2026 Tarun/PS

Tarun Kumar Gupta 2026.04.01 16:55 I attest to the accuracy and integrity of this document

You have used today's free searches. Sign in, for free, to keep searching without a limit.

Compass reads the judgments for you and finds the paragraphs for and against your question. Sign in to use it.

My Vault follows judgments for you and records every later decision that cites them. Sign in to keep one.

Sign in to download the court's PDF. The full text stays free to read here.

Sign in, for free, to download the court copy. Reading the full text here stays open to everyone.

Search and read Indian judgments without limits, save them to My Vault and find the relevant paragraphs with Compass.

Open the sign-in page instead