Manipur High Court
MC(WP(C))/759/2025 of All Manipur Contractors Association Forum And Another Vs State of Manipur and 5 Ors on 16 October 2025
IN THE HIGH COURT OF MANIPUR AT IMPHAL WP(C) No. 764 of 2025
Item No. 4-6
IN THE HIGH COURT OF MANIPUR
AT IMPHAL
WP(C) No. 764 of 2025 with
MC(WP(C) No. 759 of 2025 with
MC(WP(C) No. 721 of 2025
All Manipur Contractors Association Forum & Anr.
…..Petitioner/s
- Versus –
State of Manipur & 5 Ors.
.... Respondent/s
BEFORE
HON’BLE MR. JUSTICE A. GUNESHWAR SHARMA
Citations and Judicial Treatment
Cited by
0
Decisions in the index citing it
Cites
0
Decisions referred to
In this index
0
Of the decisions it cites
Overruled / Questioned
0
No negative treatment found
Loading the citing and cited decisions…
This judgment in the centre: on the left the decisions it cites, on the right the decisions citing it. Colour is the treatment; choose a decision to open it.
Order
17.10.2025
Present Mr. S. Rupachandra, learned senior counsel assisted by Mr. Shahidur Rahman, learned counsel on behalf of the petitioner, Mr. S. Niranjan, learned G.A. for the State respondent and Mr. BR. Sharma, learned CGC for the Central Government.
Vide order dated 03.10.2025, respondent No. 4 i.e. Secretary, Ministry of Rural Development, Government of India, New Delhi was directed to dispose of the representation submitted by the petitioners and also the proposal of the Hon’ble Governor and Chief Secretary, Government of Manipur in regard to the representation submitted by the petitioner for consideration of amendment of the NIT, especially clause 4.4 A (b) of the SBD of the NITs dated 29.08.2025 and 11.09.2025.
Today, Mr. BR. Sharma, learned CGC, submits that he has received one written intimation from the Ministry and he may be permitted to place before this Court on the next date.
Earlier interim order dated 03.10.2025 is extended till the next date.
Mr. S. Rupachandra, learned senior counsel for the petitioners, submits that he has also filed a fresh application being MC(WP(C) No. 759 of 2025 for allowing the members of the petitioners to submit technical bid in terms of the earlier order, as they could not do in terms of the earlier order before 08.10.2025.
However, Mr. S. Niranjan, learned G.A., submits that the Chief Engineer has issued a notification dated 08.10.2025 in terms of the order dated 03.10.2025 passed by this Court and the technical bid of the petitioner are deemed to be permitted to file in terms of the submission made by the learned G.A.
MC(WP(C) No. 759 of 2025 is disposed of.
List the remaining cases on 28.10.2025 in the motion column.