CCP/833/2025 of M/S KHANDELWAL CONSTRUCTION COMPANY Vs SHRI RAJESH YADAV on 20 August 2026
JUDICATURE FOR RAJASTHAN BENCH AT JAIPUR S.B. Civil Contempt Petition No. 833/2025 CNR: RJHC020682742025 | URN: CCP / 888U / 2025 M/s Khandelwal Construction Company, Through Partner Shri Manish Khandelwal, Aged About 37 Years S/o Shri Brijmohan Khandelwal, R/o Plot No. 181, Govind Nagar East,
[2026:RJ-JP:33519]
HIGH COURT OF JUDICATURE FOR RAJASTHAN
BENCH AT JAIPUR
S.B. Civil Contempt Petition No. 833/2025
CNR: RJHC020682742025 | URN: CCP / 888U / 2025
M/s Khandelwal Construction Company, Through Partner Shri Manish Khandelwal, Aged About 37 Years S/o Shri Brijmohan Khandelwal, R/o Plot No. 181, Govind Nagar East, Opp.
Bhrampuri Police Station, Amer Road, Jaipur
----Petitioner
Versus
1.
Shri Rajesh Yadav, Principal Secretary, State Of Rajasthan, Archaeology And Museum Department, Secretariat, Jaipur
2.
Shri Pankaj Dherendera, Director, Archaeology And Museum Department Rajasthan, Jaipur, Albert Hall Campus, Ramniwas Bagh, Jaipur
3.
Shri Ashish Garg, Executive Engineer, Archaeology And Museum Department, Jaipur, Albert Hall Campus, Ramniwas Bagh, Jaipur
4.
Shri Anil Mittal, Assistant Engineer, Archaeology And Museum Department, Jaipur, Albert Hall Campus, Ramnivas Bagh, Jaipur
5.
State Of Rajasthan, Through Chief Secretary To Government, Secretariat Jaipur
-- --Respondents
For Petitioner(s)
:
Mr. Sandeep Sharma
For Respondent(s)
:
Ms. Mahi Yadav, AAG
Mr. Arun Kumar, AGC
Mr. Kuldeep Singh Rathore, AAAG
HON'BLE MR. JUSTICE GANESH RAM MEENA
Citations and Judicial Treatment
Cited by
0
Decisions in the index citing it
Cites
0
Decisions referred to
In this index
0
Of the decisions it cites
Overruled / Questioned
0
No negative treatment found
Loading the citing and cited decisions…
This judgment in the centre: on the left the decisions it cites, on the right the decisions citing it. Colour is the treatment; choose a decision to open it.
Order
20/08/2026 Learned counsels appearing for the parties state that the application submitted by the petitioner has been decided by the
[2026:RJ-JP:33519] (2 of 2) [CCP-833/2025] Standing Committee vide order dated 19.08.2026, as was directed by the co-ordinate Bench of this Court on 18.11.2022. In view of the above, the present petition is disposed of. Contempt notices are discharged. However, petitioner would be at liberty to avail appropriate remedy available to him under law so as to challenge the decision of the Standing Committee, if he feels aggrieved by the same. (GANESH RAM MEENA),J 64/EKTA SAINI