Debts Recovery Tribunals and Appellate Tribunals
BANK OF MAHARASHTRA vs M/S Patni Wooden Industries on 23 April 2024
IN THE DEBTS RECOVERY TRIBUNAL, AURANGABAD
(BEFORE HON’BLE PRESIDING OFFICER, AURANGABAD)
ORDER SHEET
[APK]
23.04.2024
Sr. No.33
CA NO. 2/2024
Classific
ation
No. of
Exh.
CHAMBER APPEAL No. 2/2024
Bank Of Maharashtra
.. Applicant
Versus
M/S Patni Wooden Industries& others
.. Defendants
Mr. - Advocate for the applicant.
None for defendants
1. In this matter the objections are not removed in time despite being notified. The orders came to be passed on 06.11.2023
declining the registration.
2. The learned counsel for the applicant has filed screenshot of the list of the matters which according to him listed on 06.11.2023. It is duty of the counsel to take care of the matters, he has not bother to know date after getting free form the District Court and waited for orders which he got on 29.11.2023.
3. The Tribunal is not at all convenience, the way at which the matter has been conducted. However in the interest of justice, I
pass the following order :
Citations and Judicial Treatment
Cited by
0
Decisions in the index citing it
Cites
0
Decisions referred to
In this index
0
Of the decisions it cites
Overruled / Questioned
0
No negative treatment found
Loading the citing and cited decisions…
This judgment in the centre: on the left the decisions it cites, on the right the decisions citing it. Colour is the treatment; choose a decision to open it.
ORDER
A. Chamber Appeal No. 02/2024 is allowed. B. The Original Application (Dairy) No. 278/2023 is hereby restored to its original position. C. The applicant is directed to remove the office objections within seven days from the date of uploading the order. D. Consign the file to the Record Room and orders be uploaded on official web-site.
(Vimal Gupta) Presiding Officer Debts Recovery Tribunal, Aurangabad