Debts Recovery Tribunals and Appellate Tribunals
Canara Bank vs Mr. R. Parthasarathy on 17 August 2026
BEFORE THE DEBTS RECOVERY TRIBUNAL –II AT CHENNAI
Dated this 17th day of August, 2026
PRESENT: SHRI SHARANG DHAR UPADHYAY
PRESIDING OFFICER
TA No.517 of 2023
(Originally filed before DRT-I, Chennai as OA No.268 of 2021 and thereafter transferred to this Tribunal and renumbered as TA No.517 of 2023)
Canara Bank
Rep. by its Senior Manager
Karaikadu Branch, Virudhachalam Road
Kannarapettai, Cuddalore District
…Applicant
Versus
R. Parthasarathy
S/o K.S. Ramalingam
Pudur, Sedapalayam
Cuddalore – 607 003
…Defendant
Counsels on Record / Appeared
Counsel for Applicant Bank : Mr. Akshai Mani Defendant ex-parte on 05.08.2022
Citations and Judicial Treatment
Cited by
0
Decisions in the index citing it
Cites
0
Decisions referred to
In this index
0
Of the decisions it cites
Overruled / Questioned
0
No negative treatment found
Loading the citing and cited decisions…
This judgment in the centre: on the left the decisions it cites, on the right the decisions citing it. Colour is the treatment; choose a decision to open it.
FINAL ORDER
1. This application is filed by the applicant bank under Section 19(1) of Recovery of Debts and Bankruptcy Act, 1993 against the defendant seeking issuance of a Recovery Certificate for recovery of a sum of Rs.37,00,323/- together with interest at the rate of 10.90% p.a. with yearly rests from the date of the application till the date of realisation along with costs of the application.
2. The subject matter of the case is the Produce Loan availed by the defendant from the Applicant Bank.
3. It is the case of the applicant that the defendant approached the applicant vide Loan application dated 06.02.2019 for grant of credit facility and considering the said request the applicant sanctioned a ‘Produce Loan’ of Rs.30,00,000/- vide its sanction dated 06.02.2019. The said loan is repayable in 12 months. It is also stated that the defendant executed various loan and security documents on 06.02.2019.
4. It is also stated that the defendants failed to comply with the terms of sanction and failed to regularize the loan account despite repeated demands and hence the loan account was classified as NPA on 10.12.2021 and a recall notice was issued on 28.02.2020 followed by legal notice on 30.11.2020. Despite the said notices the defendant did not come forward clear the outstanding dues. Hence the present OA is filed for recovery of its dues.
8. Summons was taken out to the defendant and the defendant was served. As the defendant was continuously absent and as there was no representation for the defendant on 05.08.2022, the defendant was set ex- parte on that day. Applicant Bank filed Proof Affidavit along with 9 documents, which were marked as Ex. A-1 to A-9 on 13.03.2024. The Ld.
Counsel for Applicant Bank made his submissions on 04.06.2026 and thereafter the matter stood till this date for passing final orders.
9. The following issues arise for consideration in the matter: - (a) Whether the applicant had succeeded in proving the liability of the defendant?
(b) What order as to cost of the proceedings need be passed?
These issues are considered together.
10. Heard the Ld. Counsel for the applicant, perused the OA averments and the record placed before the Tribunal.
11. The evidence of the applicant is led by AW1 who produced the documents Exhibit A-1 to A-9 along with the proof affidavit. The documents produced in evidence are all found admissible. The proof affidavit of the applicant bank remained unchallenged and unrebutted. Therefore, on careful consideration of proof affidavit along with exhibits filed on behalf of the applicant bank, besides the material placed before the Tribunal, the Tribunal is satisfied that the applicant bank has successfully proved the OA claim against the defendant. Further, the statement of accounts in respect of the loan account produced and certified under the Banker’s Book Evidence Act, clearly indicates that the amount claimed by the applicant is due from the defendant. It is clear from the statement of accounts that penal interest is not capitalized.
12. In view of the foregoing, it is clearly evident that the application filed by the applicant bank is well within the period of limitation and this Tribunal possesses the territorial and pecuniary jurisdiction to entertain this OA.
13. In view of the fact that the loan facility availed by the defendant is a produce loan and the applicant has claimed interest at contractual rate till the date of filing of the OA, this Tribunal is of the view that the pendente lite interest can be awarded at reduced rates.
14. In view of the afore mentioned discussions, the only conclusion this Tribunal can draw is that the applicant had clearly proved the disbursement of the loan, which the applicant is entitled to realize. Hence, OA is disposed off in the following manner: - (a) TA No.517 of 2023 stands allowed.
(b) Applicant is permitted to realize an aggregate sum of Rs.37,00,323/- with further interest @8% per annum (simple) from the date of filing of the application till the date of realization in full, from the defendant after deducting all the amounts received / realized by them during the pendency of OA and also by selling the other assets of the defendant.
(c) It is made clear that the defendant is personally liable for all such amounts due as ordered above.
(d) Applicant is permitted to realize cost of the proceedings and shall file cost memo within 15 days from the date of receipt of the copy of the order.
(e) The Recovery Certificate shall be drawn up and issued to the Recovery Officer in terms of this final order.
15. Communicate a copy of the order to the parties concerned in terms of Section 19(21)(i) of the RDB Act, read with Rule 16 of DRT (Procedure) Rules, 1993.
Sd/-
(Dictated to PS, who typed in the system directly, corrected, signed and pronounced by me in Open Court, on this 17th day of August, 2026)
EXHIBITS MARKED BY APPLICANT BANK
S. No. Date Description of Documents Exhibit Nos.
1. 06.02.2019 Loan Application A-1
2. 06.02.2019 Sanction Memorandum A-2
3. 06.02.2019 Demand Promissory Note executed by defendant. A-3
4. 06.02.2019 Letter for loans and advances A-4
5. 06.02.2019 Take delivery letter A-5
S. No. Date Description of Documents Exhibit Nos.
6. 06.02.2019 Lien letter to Warehouse A-6
7. 28.02.2020 Recall Notice by applicant bank A-7
8. 30.11.2020 Legal notice by applicant bank A-8
9. Statement of Accounts along with certificates under Bankers’ Book Evidence Act. A-9
Sd/-
DESCRIPTION OF PROPERTY
NIL
Sd/-