BEFORE THE DEBTS RECOVERY TRIBUNAL –II AT CHENNAI

Dated this 28th day of March, 2024

PRESENT: SHRI T. RAJESH

PRESIDING OFFICER

TA No.403 of 2022

(Originally filed before DRT-I Chennai as OA No.163 of 2019 and thereafter transferred to this Tribunal and renumbered as TA No.403 of 2022)

Canara Bank

(Erstwhile Syndicate Bank)

Vaniyambadi Branch

Represented by its Deputy Regional Manager Regional Office-II

No.2/3, 2nd Floor, Gurumisiri Complex

Kamarajar Street, Tambaram West

Chennai – 600 045

…Applicant

Versus

1.

Mr. V. Senthil Kumar

S/o. Mr. M Vadivel

No.1/27A, Karapattu Village & Post

Vaniyambadi Taluk, Vellore-635751

2.

Mr. M Vadivel

S/o. Muthu Sami

Karapattu Village & Post

Vaniyambadi Taluk, Vellore-635751

Counsel for the Applicant Bank

Counsel for Defendants

:

:

M/s K.V. Subramanian Associatez

M/s G. Desingu

Citations and Judicial Treatment

No citing decisions in the index yet

Cited by

0

Decisions in the index citing it

Cites

0

Decisions referred to

In this index

0

Of the decisions it cites

Overruled / Questioned

0

No negative treatment found

Loading the citing and cited decisions…

FINAL ORDER

1. The Application is filed Under Section 19 (1) of the Recovery of Debt And Bankruptcy Act, 1993 seeking for issuance of a Recovery Certificate for Rs. 28,03,249/- due in the Agricultural loan availed by the defendants from the earst while Syndicate Bank, which got amalgamated with applicant bank.

2. The above TA was originally filed before DRT-I and got transferred to this Tribunal and renumbered as above.

3. The applicant contends that the credit facility of Rs.7,10,000/- was availed by the 1st defendant as the borrower and the 2nd defendant as the stood as a guarantor. The facility was availed for the purchase of tractor, agricultural implements and trailer. It is also stated that the facility is secured by mortgage of the schedule properties.

4. The Applicant further contents that despite availing the credit facility by obliging to pay back the amount, the defendant failed in compliance of the same and all the efforts of the Applicant to make the defendants pay back the amount failed forcing the Applicant to file this Application.

5. The defendants entered appearance and filed their reply statement denying the TA averments. It is contended that only due to draught, the defaults occurred. The defendants are also disputing the OA claim and contend that the applicant had charged exorbitant interest.

6. The Applicant let in evidence through AW1, filed proof affidavit in conforming with pleading and got marked Ext A1 to A10. No defense evidence was let in by the defendants, though sufficient opportunity was given.

7. Heard, the following issues arise for consideration: - (a) Whether the Applicant had proved the TA claim?

(b) What orders are to be passed? Both these issues are decided together

8. The Applicant’s evidence remained un-rebutted. Though a reply statement was filed no specific denial was put forth other than a general denial of facts. No defense evidence was adduced in rebuttal of the TA claim. The documents produced by the Applicant are found to be admissible and are sufficient to prove the TA claim. Hence the Applicant is to be found entitled for the TA claim. The TA claim is made within limitation and there is no capitalization of penal interest. Since the TA claim is arrived at by calculating interest at the contractual rate, which is on the higher side, and also taking note of the fact that the credit facility is for agricultural purpose, pendente lite and future interest is awarded at 8% simple.

9. In view of the above, the following order is passed: - (a) TA No. 403 of 2022 stands allowed.

(b) Applicant is permitted to recover an amount of Rs. 28,03,249/- with future and pendente lite interest @ 8% simple per annum from the date of filing of the OA/TA till realization, after giving credit to all the amount recovered and received during the pendency of the OA/TA, from the defendants jointly, severally, personally and also by proceeding against their assets including the scheduled properties.

(c) A Recovery Certificate is to be drawn and issued to the recovery Officer to enable recovery of the as per the above terms.

(d) Applicant is allowed to realize cost of the proceeding for which cost memo is to be filed in 7 days’ time from the date of receipt of the copy of the order.

10. Communicate a copy of the order to the parties concerned in terms of section 19(21)(i) of the RDB Act, read with Rule 6 of DRT (Procedure) Rules, 1993. (Dictated to PS, transcribed by him, corrected, signed and pronounced by me in Open Court, on this the 28th day of March, 2024) Sd/- (T. RAJESH) PRESIDING OFFICER DRT-II, CHENNAI

You have used today's free searches. Sign in, for free, to keep searching without a limit.

Compass reads the judgments for you and finds the paragraphs for and against your question. Sign in to use it.

My Vault follows judgments for you and records every later decision that cites them. Sign in to keep one.

Sign in to download the court's PDF. The full text stays free to read here.

Sign in, for free, to download the court copy. Reading the full text here stays open to everyone.

Search and read Indian judgments without limits, save them to My Vault and find the relevant paragraphs with Compass.

Open the sign-in page instead