Debts Recovery Tribunals and Appellate Tribunals
HUDCO Ltd vs Smt D Murugumani on 29 December 2023
IN THE DEBT RECOVERY TRIBUNAL –II CHENNAI
Dated this 29th day of December, 2023
PRESENT: SHRI T.RAJESH
PRESIDING OFFICER
T.A.No.893 of 2023
(Old OA.No.340/2018–DRT-I, Chennai)
Housing and Urban
Development Corporation Ltd.,
CMDA Tower I,
Gandhi Irwin Road, Egmore,
Chennai – 600 008.
… Applicant.
Vs.
1. Smt.D.Murugumani,
W/o.M.Kalaichelvan,
No.2/190, Rajiv Nagar,
Alagappa Nagar, Rajagambiram,
Othakadai,
Madurai.
2. Mr.M.Kalaichelvan,
S/o.S.P.Munjandipillai,
No.2/190, Rajiv Nagar,
Alagappa Nagar, Rajagambiram,
Othakadai,
Madurai.
3. Mr.D.Jeyarajan,
No.10, Bamban Road,
Thangaiah Nadar Compound,
Veerapillai North Road, Mahalipatti,
Madurai – 625 009.
… Defendants.
Counsel for Applicant
: M/s.Deepa Harigovind.
Defendants
: Exparte.
……
Citations and Judicial Treatment
Cited by
0
Decisions in the index citing it
Cites
0
Decisions referred to
In this index
0
Of the decisions it cites
Overruled / Questioned
0
No negative treatment found
Loading the citing and cited decisions…
This judgment in the centre: on the left the decisions it cites, on the right the decisions citing it. Colour is the treatment; choose a decision to open it.
ORDER
1. The above Transfer Application is filed under section 19 of the Recovery of Debts and Bankruptcy Act seeking recovery of Rs.10,68,599/- with further interest from the date of filing of the TA and by allowing the same to be recovered from the defendants jointly and severally and also by sale of the schedule mentioned properties.
2. The above original application is filed before the DRT-I and stood transferred to this Tribunal and renumbered as above.
3. The case of the applicant can be encapsulated as follows: The defendants approached the applicant for availing a Housing loan for Rs.7,00,000/- which was sanctioned and disbursed by the applicant. The 3rd defendant stood as a guarantor to the said credit facility.
4. It is also stated that the above facilities were availed after execution of necessary loan documents obliging themselves to repay the amount promptly and regularly, without fail.
5. Apart from execution of the necessary loan documents, the 1st defendant had created security by way of equitable mortgage over the schedule mentioned properties.
6. Even though the defendants had obliged themselves to repay the amount promptly and regularly, they failed to do so resulting defaults in the account and the same being declared as NPA on 31.07.2011.
7. The applicant’s officials had on many occasions approached the defendants requesting them to regularize the account and despite the same, no effort was made by the defendants to get the account regularized over to pay back the amount. Even as no repayment was made despite repeated requests, the applicant had on 02.06.2015 caused to issue a demand notice requiring repayment of the amount due in the account.
8. It is also the case of the applicant that despite repeated reminders and requests, the defendants had failed to make the repayment forcing the applicant to file this TA seeking recovery of the amount due in the account with further interest and cost.
9. Even as the defendants failed to enter appearance, they were set exparte on 27.09.2022.
10. The applicant had let in evidence through AW1 who had sworn to a Proof Affidavit in terms of the pleadings in the TA and also produced Exhibits A1 to A 20 and got the same marked in evidence.
11. Heard the counsel for the applicant and considered the contentions as taken in the TA in the light of documentary evidence and proof affidavit. The following issues arise for consideration in this matter: i) Whether the applicant had succeeded in proving the TA claim? ii) What orders are to be passed? Both these issues are gone into and decided together.
12. The case put forth by the applicant in the Application remains unrebutted as defendants remain exparte. The evidence tendered by the applicant remains uncontroverted and undisputed. The evidences put forth by the applicant were found admissible. From the statement of accounts as produced by the applicant, it is evident that the amount as claimed in the TA is outstanding in the account, which the applicant is entitled to get recovered from the defendants and their assets (including the schedule mentioned properties). The claim of the applicant is well within the period of limitation and there is no Capitalization of penal interest. Since the facility is a Housing Loan and TA claim is arrived at by calculating interest at agreed rate the pendentelite and future interest is awarded at simple rate. The prayer for interest compounding monthly and additional interest is declined.
13. In view of the finding as entered above i) TA No.893/2023 stands allowed. ii) Applicant is permitted to recover an amount of Rs.10,68,599/-(Rupees Ten Lakhs Sixty Eight Thousands Five Hundred and Ninety nine only) with future and pendentelite interest @9.25% p.a. (simple) from the date of filing of the TA till realization from the defendants after giving credit to all the amounts recovered and received during the pendency of the TA. iii) The schedule property to be proceeded against and sold and if the sale proceeds are not sufficient the defendants and their other assets are liable to be proceed against. iv) A Recovery Certificate is to be drawn and issued to the recovery officer to enable recovery of the amount as per the above terms. v) Applicant is allowed to realize cost of the proceedings for which cost memo is to be filed in 7 days’ time from the date of receipt of the copy of the order.
14. Communicate a copy of the order to the parties concerned in terms of Section 19(21)(i) of the RDB Act, read with Rule 16 of DRT (Procedure) Rules, 1993. (Dictated to PA, transcribed by him, corrected, signed and pronounced by me in the Open Court, this 29th day of December, 2023)
Sd./- (T. RAJESH) PRESIDING OFFICER DRT-II, CHENNAI