IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA

CWP No.91 of 2026

Date of Decision: 13.10.2026 _____________________________________________________________________ Nirmala Devi ……...Petitioner Versus HPSEBL and Ors. …....Respondents

Coram

Hon’ble Mr. Justice Sandeep Sharma, Judge. Whether approved for reporting?

For the Petitioner: Mr. Ashok Kumar Verma, Advocate.

For the Respondents: Ms. Sunita Sharma, Senior Advocate with Mr. Dhananjay Sharma, Advocate. __________________________________________________________________________

Sandeep Sharma, J. (Oral)

Precisely, the case of the petitioner as has been highlighted in the petition and further canvassed by Mr. Ashok Kumar Verma, learned counsel representing the petitioner is that though petitioner is ready and willing to provide right of way for service wire, but since respondent-Electricity Board has laid service wire over the slab of the first floor of the house of the petitioner, she is unable to raise construction of second floor.

2. On instructions, learned counsel representing the petitioner states that the petitioner has no objection in case service wire is taken from the side of her house and in that regard, she is also ready and willing to pay the expenditure, if any, incurred for shifting of wires. High Court of H.P. ::: Downloaded on - 28/10/2026 17:17:16 :::CIS

2

3. Ms. Sunita Sharma, learned Senior Counsel, while responding to the plea taken at the behest of the petitioner states that though by now it is well settled that right of way is to be provided by the consumer, but in case petitioner furnishes an undertaking that she shall have no objection in case service wire is laid alongside her house and she will bear the expenditure of shifting of wire, needful shall be done expeditiously.

4. Consequently, in view of the above, present petition is disposed of with a direction to respondent-Electricity Board to shift the electricity wire, which at present is hanging over the slab of first floor of the house, to the side of the house of the petitioner, subject to her furnishing undertaking that she shall have no objection in case service wire is taken from the side of her house and she will bear the cost of shifting. Needful in terms of instant order shall be done expeditiously, preferably within a period of one week from the date of depositing the cost of shifting, which shall be indicated by respondent- Electricity Board within a period of one week from the date of receipt of the order. Pending applications, if any, stand disposed of accordingly.

October 13, 2026

(Sandeep Sharma), (manjit)

Judge High Court of H.P. ::: Downloaded on - 28/10/2026 17:17:16 :::CIS

You have used today's free searches. Sign in, for free, to keep searching without a limit.

Compass reads the judgments for you and finds the paragraphs for and against your question. Sign in to use it.

My Vault follows judgments for you and records every later decision that cites them. Sign in to keep one.

Sign in to download the court's PDF. The full text stays free to read here.

Sign in, for free, to download the court copy. Reading the full text here stays open to everyone.

Search and read Indian judgments without limits, save them to My Vault and find the relevant paragraphs with Compass.

Open the sign-in page instead