Madras High Court
CRP/3741/2023 of L.CHANDRAN Vs STATE BANK OF INDIA on 8 October 2026
CRP.No.3741 of 2023
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 08-10-2026
CORAM
THE HON'BLE MR.JUSTICE S. SOUNTHAR
CRP.No.3741 of 2023
CNR:{HCMA011135842023}
1. L.Chandran
2. Saradha
..Petitioner(s)
Vs
M/s.State Bank Of India, Agalar,
Reptd. By its Branch Manager,
A.Rakesh, (M/A 31)
S/o A.Vikram,
Ootacamund, The Nilgiris.
..Respondent(s)
PRAYER: Civil Revision Petition is filed under Section 115 of the Civil Procedure Code, to set aside the Fair and Decreetal Order dated 17.11.2022
passed by the learned Judge of Subordinate Court at Udhagamandalam in
I.A.No.1 of 2022 in O.S.No.150 of 2014.
For Petitioners
: Mr.Thangavadhanabalakrishnan
For Respondent
: Not Ready in Notice
Citations and Judicial Treatment
Cited by
0
Decisions in the index citing it
Cites
0
Decisions referred to
In this index
0
Of the decisions it cites
Overruled / Questioned
0
No negative treatment found
Loading the citing and cited decisions…
This judgment in the centre: on the left the decisions it cites, on the right the decisions citing it. Colour is the treatment; choose a decision to open it.
ORDER
The Civil Revision Petition is filed challenging the order passed by the Subordinate Court at Udhagamandalam in I.A.No.1 of 2022 in O.S.No.150 of 2014, 17.11.2022, dismissing the application filed by the petitioners seeking to
CRP.No.3741 of 2023
condone the delay of 2480 days in filing the petition to set aside the exparte decree passed against the petitioners.
2. The respondent herein filed a suit for recovery of money based on the mortgage. In the said suit, an exparte decree was passed as against the petitioners on 04.07.2015. The petitioners filed an application seeking to set aside the exparte decree and to condone the delay of 2480 days in filing such application on 18.04.2022. The condone delay petition was dismissed by the Trial Court and aggrieved by the same, the petitioners have come before this Court.
3. The learned counsel appearing for the petitioners would submit that at the relevant point of time, there was negotiation between the bank and the Floricultural Farmers Association and in view of the same, the petitioners failed to file written statement and give suitable instructions to their counsel. The learned counsel for the petitioner further submits that due to covid pandemic also, the petitioners could not file the petition to set aside the exparte decree in time.
4. A perusal of the typed-set of papers would indicate that the exparte decree against the petitioner was passed as early as 04.07.2015. The covid
CRP.No.3741 of 2023
pandemic had taken place only in March-2020. Therefore, the pandemic situation will not explain the delay of 2480 days in this case. Further, the petitioners stated that there was negotiation between the Floricultural Farmers Association and the bank regarding the settlement of loan and hence, the petitioners could not file written statement in time. The petitioners have not placed any material to substantiate said the averment.
5. Further, merely because there was negotiation between the parties, the petitioners cannot ignore the summons issued by the Court and be negligent in following up the case. The reason given by the petitioners cannot be accepted to explain the inordinate delay of 2480 days. I do not find any error in the impugned order.
6. Accordingly, the Civil Revision Petition is dismissed. No costs. 08-10-2026 Index: Yes/No Speaking/Non-speaking order Neutral Citation: Yes/No dm To The Subordinate Court, Udhagamandalam.