Gujarat High Court
SCA/24904/2006 of VIJAYBHAI B.JOSHI Vs TORRENT POWER AEC LTD. THR' GENERAL MANAGER on 27 December 2006
IN THE HIGH COURT OF GUJARAT AT AHMEDABAD SPECIAL CIVIL APPLICATION No. 24904 of 2006 For Approval and Signature: HONOURABLE MR.JUSTICE J.M.PANCHAL HON'BLE SMT. JUSTICE ABHILASHA KUMARI ========================================================= 1 Whether Reporters of Local Papers may be
Citations and Judicial Treatment
Cited by
0
Decisions in the index citing it
Cites
0
Decisions referred to
In this index
0
Of the decisions it cites
Overruled / Questioned
0
No negative treatment found
Loading the citing and cited decisions…
This judgment in the centre: on the left the decisions it cites, on the right the decisions citing it. Colour is the treatment; choose a decision to open it.
Issues
IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
SPECIAL CIVIL APPLICATION No. 24904 of 2006
For Approval and Signature:
HONOURABLE MR.JUSTICE J.M.PANCHAL
HON'BLE SMT. JUSTICE ABHILASHA KUMARI
=========================================================1[Whether Reporters of Local Papers may be allowed ]to see the judgment ?
2To be referred to the Reporter or not ?
3[Whether their Lordships wish to see the fair copy ]of the judgment ?
Whether this case involves a substantial question of law as to the interpretation of the 4constitution of India, 1950 or any order made thereunder ?
5[Whether it is to be circulated to the civil judge ]?
=========================================================
VIJAYBHAI B.JOSHI - Petitioner
Versus
TORRENT POWER AEC LTD. THR' GENERAL MANAGER & 2 - Respondents =========================================================
Appearance :
MRS FALGUNI D PATELfor Petitioner.NOTICE NOT RECD BACK for Respondent(s) : 1 - 3.NOTICE SERVED BY DS for Respondent(s) : 1 - 3.=========================================================
CORAM :HONOURABLE MR.JUSTICE J.M.PANCHAL
and
HON'BLE SMT. JUSTICE ABHILASHA KUMARI
Date : 27/12/2006
ORAL JUDGMENT
(Per : HONOURABLE MR.JUSTICE J.M.PANCHAL)
Rule. The endorsement on the board indicates that all the respondents are duly served with notice for final disposal of the petition. However, none of the respondents has appeared either through its Lawyer or through its constituted agent, nor any of them has filed reply controverting the averments made in the petition. Therefore, this Court is of the opinion that it is not necessary for the petitioner to effect service of notice of rule issued in the instant petition upon the respondents. Having regards to the facts of the case, the petition is taken up for final disposal today.
2. By filing this petition under Article 226 of the Constitution, the petitioner has prayed to direct the respondent No.1 i.e. The Torrent Power A.E.C.Ltd., to grant 14 electric connections to the residential petitioner.
Units constructed by the
3. The record shows that the land bearing
Revenue Survey No.270/2 Paiki of Town Planning Scheme No.20-B of village Kali, Taluka : City, District : Ahmedabad belonged Mr.Rasikbhai Babaldas and others. The petitioner i.e. Vijaybhai B.Joshi, as power of attorney holder of the owner of the land, applied to Ahmedabad Urban Development Authority to grant development permission. The development permission was granted to the petitioner on August 12, 2005, which is quite evident from the contents of document produced at Annexure-A to the petition. The case of the petitioner is that after obtaining development permission, he has constructed 14 row-houses. After construction of the row-houses was over, it was the duty of the petitioner to obtain Building Use Permission and thereafter to apply to the respondent No.1 for supply of electric connection to the row-houses constructed by him. However, without obtaining
Arguments
Building Use Permission, the petitioner applied to the respondent No.1 for supply of electric connections to the residential Units constructed by him. The said request has been turned down by the respondent No.1, which is quite evident from the contents of letter dated November 14, 2006 addressed by General Manager of the respondent No.1 to the petitioner, a copy of which is produced by the petitioner at Annexure-B to the petition. By the said communication, the petitioner has been called upon to produce Building Use Permission to enable the respondent No.1 to supply electricity connection to the residential Units constructed by him. Under the circumstances, the petitioner has filed the instant petition and claimed reliefs to which reference is made earlier.
4. The petition was placed for admission hearing on December 1, 2006 and after hearing the learned Counsel for the petitioner, notice for final disposal of the petition was issued. As observed earlier, all the respondents are duly served, but, none of them has appeared before the Court nor contested the petition.
5. This Court has heard Ms. Falguni D.Patel, learned Counsel for the petitioner and considered the documents forming part of the petition. Having regard to the facts of the case, this Court is of the opinion that interest of justice would be served if the following directions are issued:
(1) The petitioner will approach the Ahmedabad Urban Development Authority for obtaining Building Use Permission within thirty days from today with a proper application/form/format and by paying requisite fee, if any.
(2) The Ahmedabad Urban Development Authority is directed to take decision on the application, which may be submitted by the petitioner, within four months from the date of receipt of the same.is directed to take decision on the application, which may be submitted by the petitioner, within four months from the date of receipt of the same.
(3) The petitioner shall apply to the respondent No.1., i.e. Torrent Power AEC Limited, for providing electricity connection to 14 row-houses constructed byhimwithaproper application/form/format and by paying charges within a week.
(4) The respondent No.1, i.e. Torrent Power AEC Limited, is directed to provide electricity connection to 14 row-houses constructed by the petitioner within one month on usual terms and conditions.
(5) In case the Ahmedabad Urban Development Authority is not approached by the petitioner for obtaining Building Use Permission within the period stipulated in this order, the Ahmedabad Urban Development Authority shall inform the Torrent Power AEC Limited to disconnect the electricity supply made available to 14 row-houses constructed by the petitioner and in such an eventuality, it would be open to the Torrent Power AEC Limited to disconnect the electricity supply provided to the residential Units constructed by the petitioner within a period of fifteen days.
(6) In case the Ahmedabad Urban Development
Authority does not grant Building Use
Permission, it will ask the Torrent Power AEC Limited to disconnect the electricity supply provided to 14 row-houses constructed by the petitioner within a period of fifteen days and, thereupon, it would be open to the Torrent Power AEC
Limited to disconnect the electricity supply provided to the residential Units constructed by the petitioner.
(7) The petitioner shall file an Undertaking before the Torrent Power AEC Limited to the effect that in the event the Building before the Torrent Power AEC Limited to the effect that in the event the Building Use Permission is not granted by the Ahmedabad Urban Development Authority,
the petitioner will have no objection to disconnection of electricity supply provided to 14 row-houses constructed by him. This Undertaking shall be filed along with the application/form/format meant for the purpose.
Rule is made absolute subject to above
referred to directions. There shall be no order as to costs. Direct Service is permitted.