Supreme Court of India

DELHI DEVELOPMENT AUTHORITY versus RAMBIR AND ORS on 20 January 2023

Cites 6, Cited by 0

DELHI DEVELOPMENT AUTHORITY

v.

RAMBIR AND ORS.

(Civil Appeal No.362 of 2023)

JANUARY 20, 2023

[M. R. SHAH AND C.T RAVIKUMAR, JJ.]

Right to Fair Compensation and Transparency in LandAcquisition, Rehabilitation and Resettlement Act, 2013 – s.24(2) –Land Acquisition Act, 1894 – High Court relying on the decision inPune Municipal Corporation case declared that the acquisitionproceeding initiated under the 1894 Act w.r.t the subject lands isdeemed to have lapsed u/s.24(2) – On appeal, held: Decision inPune Municipal Corporation case has been overruled by the decisionof Constitution bench in Indore Development Authority case –Applying the law laid down in Indore Development Authority andmore particularly, considering the fact that the possession of theland in question was taken over in the year 2007 and handed overto the beneficiary department, the impugned judgment passed bythe High Court is set aside.

Indore Development Authority v.Manoharlal and Ors. (2020) 8 SCC 129 : [2020] 3 SCR 1 –followed.

Pune Municipal Corporation and Anr. vs.HarakchandMisirimal Solanki and Ors. (2014) 3 SCC 183 : [2014]1 SCR 783 – referred to.

Case Law Reference

[2014] 1 SCR 783 referred toPara 2[2020] 3 SCR 1 followedPara 2

CIVIL APPELLATE JURISDICTION : Civil Appeal No.362 of2023.

From the Judgment and Order dated 20.12.2017 of the High Courtof Delhi at New Delhi in WP (C) No.5441 of 2017.

901

A

B

C

D

E

F

G

H

AAtul Kumar, Ms. Sweety Singh, Ms. Archana Kumari, RahulPandey, Avs Kadyan, Rajiv Ranjan, Mishra Saurabh, Ms. SujeetaSrivastava, Nishit Agrawal, Ms. Kanishka Mittal, Ms. Vanya Agrawal,Ashwani Kumar, Anshay Dhatwalia, Ms. Binu Tamta, Ms. Smita Maan,Nitin Mishra, Ishaan Sharma, Mohit Kumar Gupta, Shekhar Yadav, Ms.BIti Sharma, Rahul Bhatia, Rachita Kadyan, N. S. Vashist, Gagan Gupta,Ms. Astha Tyagi, Dinesh Chander Trehan, Ms. Diksha Narula, Advs.for the appearing parties.

The Judgment of the Court was delivered by CM. R. SHAH, J.

Citations and Judicial Treatment

No citing decisions in the index yet

Cited by

0

Decisions in the index citing it

Cites

6

Decisions referred to

In this index

6

Of the decisions it cites

Overruled / Questioned

0

No negative treatment found

Loading the citing and cited decisions…

1. Feeling aggrieved and dissatisfied with the impugnedjudgmentand order passed by the High Court of Delhi at New Delhi inWrit Petition(C) No. 5441 of 2017 by which the High Court has allowedDthe said writ petition and has declared that the acquisition proceedingsinitiated under the Land Acquisition Act, 1894 (hereinafter referred toas “Act, 1894”) with regard to the land in question is deemed to havelapsed under Section 24(2) of the Right to Fair Compensation andTransparency in Land Acquisition, Rehabilitation and Resettlement Act,E2013 (hereinafter referred to as “Act, 2013”), the Delhi DevelopmentAuthority (DDA) has preferred the present appeal.

2. Having heard the learned counsel appearing on behalf of therespective parties and having gone through the impugned judgment andForder passed by the High Court, it appears that it was the specific caseon behalf of the LAC/DDA before the High Court and so stated in thecounter filed that the possession of the land in question was taken overand handed over to the beneficiary department in the year 2007. Despitethe above and relying upon the earlier decision of this Court in the caseGof Pune Municipal Corporation and Anr. Vs. HarakchandMisirimal Solanki and Ors., (2014) 3 SCC 183, the High Court hasdeclared that the acquisition with respect to the land in question is deemedto have lapsed on the ground that the compensation was not tendered tothe original landowners as per Section 31 of the Act, 1894. However,Hthe decision of this Court in the case of Pune Municipal Corporation DELHI DEVELOPMENT AUTHORITY v. RAMBIR AND ORS.[M. R. SHAH, J.]

and Anr. (supra) has been specifically overruled by the ConstitutionBench of this Court in the case of Indore Development AuthorityVs. Manoharlal and Ors., (2020) 8 SCC 129. In paragraphs 365 and366, the Constitution Bench of this Court has observed and held as under:-

“365. Resultantly, the decision rendered in Pune MunicipalCorpn. [Pune Municipal Corpn. v. Harakchand Misirimal Solanki,(2014) 3 SCC 183] is hereby overruled and all other decisions inwhich Pune Municipal Corpn. [Pune Municipal Corpn. v.Harakchand Misirimal Solanki, (2014) 3 SCC 183] has beenfollowed, are also overruled. The decision in Sree Balaji NagarResidential Assn. [Sree Balaji Nagar Residential Assn. v. Stateof T.N., (2015) 3 SCC 353] cannot be said to be laying downgood law, is overruled and other decisions following the same arealso overruled. In Indore Development Authority v. Shailendra[(2018) 3 SCC 412], the aspect with respect to the proviso toSection 24(2) and whether “or” has to be read as “nor” or as“and” was not placed for consideration. Therefore, that decisiontoo cannot prevail, in the light of the discussion in the presentjudgment.

366. In view of the aforesaid discussion, we answer thequestions as under:

366.1. Under the provisions of Section 24(1)(a) in case theaward is not made as on 1-1-2014, the date of commencement ofthe 2013 Act, there is no lapse of proceedings. Compensation hasto be determined under the provisions of the 2013 Act.

366.2. In case the award has been passed within thewindow period of five years excluding the period covered by aninterim order of the court, then proceedings shall continue asprovided under Section 24(1)(b) of the 2013 Act under the 1894Act as if it has not been repealed.

366.3. The word “or” used in Section 24(2) betweenpossession and compensation has to be read as “nor” or as “and”.

A

B

C

D

E

FG

H

A

B

C

D

E

F

G

H

The deemed lapse of land acquisition proceedings under Section24(2) of the 2013 Act takes place where due to inaction ofauthorities for five years or more prior to commencement of thesaid Act, the possession of land has not been taken norcompensation has been paid. In other words, in case possessionhas been taken, compensation has not been paid then there is nolapse. Similarly, if compensation has been paid, possession hasnot been taken then there is no lapse.

366.4. The expression “paid” in the main part of Section24(2) of the 2013 Act does not include a deposit of compensationin court. The consequence of non-deposit is provided in the provisoto Section 24(2) in case it has not been deposited with respect tomajority of landholdings then all beneficiaries (landowners) as onthe date of notification for land acquisition under Section 4 of the1894 Act shall be entitled to compensation in accordance with theprovisions of the 2013 Act. In case the obligation under Section31 of the Land Acquisition Act, 1894 has not been fulfilled, interestunder Section 34 of the said Act can be granted. Non-deposit ofcompensation (in court) does not result in the lapse of landacquisition proceedings. In case of non-deposit with respect tothe majority of holdings for five years or more, compensation underthe 2013 Act has to be paid to the “landowners” as on the date ofnotification for land acquisition under Section 4 of the 1894 Act.

366.5. In case a person has been tendered the compensationas provided under Section 31(1) of the 1894 Act, it is not open tohim to claim that acquisition has lapsed under Section 24(2) dueto non-payment or non-deposit of compensation in court. Theobligation to pay is complete by tendering the amount under Section31(1). The landowners who had refused to accept compensationor who sought reference for higher compensation, cannot claimthat the acquisition proceedings had lapsed under Section 24(2)of the 2013 Act.

366.6. The proviso to Section 24(2) of the 2013 Act is tobe treated as part of Section 24(2), not part of Section 24(1)(b).

366.7. The mode of taking possession under the 1894 Actand as contemplated under Section 24(2) is by drawing of inquestreport/memorandum. Once award has been passed on takingpossession under Section 16 of the 1894 Act, the land vests inState there is no divesting provided under Section 24(2) of the2013 Act, as once possession has been taken there is no lapseunder Section 24(2).

366.8. The provisions of Section 24(2) providing for adeemed lapse of proceedings are applicable in case authoritieshave failed due to their inaction to take possession and paycompensation for five years or more before the 2013 Act cameinto force, in a proceeding for land acquisition pending with theauthority concerned as on 1-1-2014. The period of subsistence ofinterim orders passed by court has to be excluded in thecomputation of five years.

366.9. Section 24(2) of the 2013 Act does not give rise tonew cause of action to question the legality of concludedproceedings of land acquisition. Section 24 applies to a proceedingpending on the date of enforcement of the 2013 Act i.e. 1-1-2014.It does not revive stale and time-barred claims and does not reopenconcluded proceedings nor allow landowners to question thelegality of mode of taking possession to reopen proceedings ormode of deposit of compensation in the treasury instead of courtto invalidate acquisition.”

3. Applying the law laid down by this Court in the case of IndoreDevelopment Authority (supra) to the facts of the case on hand, and,more particularly, considering the fact that the possession of the land inquestion was taken over in the year 2007 by drawing the panchnama /possession report and was handed over to the beneficiary department,the impugned judgment and order passed by the High Court isunsustainable and the same deserves to be quashed and set aside and isaccordingly quashed and set aside, AB

C

D

E

F

G

H

906SUPREME COURT REPORTS

[2023] 1 S.C.R.

APresent appeal is accordingly allowed. No costs.

Pending application, if any, also stands disposed of.

Divya PandeyB(Assisted by : Abhishek Agnihotri, LCRA)

Appeal allowed.

C

D

E

F

G

H

You have used today's free searches. Sign in, for free, to keep searching without a limit.

Compass reads the judgments for you and finds the paragraphs for and against your question. Sign in to use it.

My Vault follows judgments for you and records every later decision that cites them. Sign in to keep one.

Sign in to download the court's PDF. The full text stays free to read here.

Sign in, for free, to download the court copy. Reading the full text here stays open to everyone.

Search and read Indian judgments without limits, save them to My Vault and find the relevant paragraphs with Compass.

Open the sign-in page instead