Sikkim High Court

Arb.P./2/2022 of M/S MAHABIR PRASAD AGARWAL Vs UNION OF INDIA AND ORS. on 17 March 2023

Cites 0, Cited by 0

COURT OF SIKKIM : GANGTOK Record of Proceedings Page 1 of 3 Arb.P. No. 02/2022 M/S MAHABIR PRASAD AGARWAL PETITIONER (S) VERSUS UNION OF INDIA & ORS. RESPONDENT (S) For Petitioner : Ms. Pritima Sunam and Ms. Pema Dechen Bhutia, Advocates. For Respondents : Ms. Sangita Pradhan, Dy. Solicitor

Arb.P. No. 02/2022

Date: 17/03/2023

CORAM :

HON’BLE MR. JUSTICE BISWANATH SOMADDER, CHIEF JUSTICE …

Citations and Judicial Treatment

No citing decisions in the index yet

Cited by

0

Decisions in the index citing it

Cites

0

Decisions referred to

In this index

0

Of the decisions it cites

Overruled / Questioned

0

No negative treatment found

Loading the citing and cited decisions…

J U D G M E N T

This is an application filed under section 11 of the Arbitration and Conciliation Act, 1996 (as amended till date), for appointment of an Arbitrator. It has been filed by a partnership firm by the name of M/s Mahabir Prasad Agarwal. This partnership firm has its office situated at Namchi in the district of Namchi, Sikkim. From the pleadings it appears that the petitioner entered into a contractual agreement with the Executive Engineer of the Central Public Works Department, Gangtok Central Division, Government of India (hereinafter referred to as E.E., CPWD, GCD) for the purpose of construction of Regional Museum of Natural History at Marchak, Gangtok, Sikkim, following acceptance of tender on 28[th] July, 2016. The total work was estimated to the tune of Rupees twenty-five crores six lakhs seventy thousand three hundred eighty-three and paise forty-seven only. In the said letter of acceptance dated 28[th] July, 2016, it has also been stated that the petitioner’s letter dated 10[th] June, 2016, shall form part of the agreement.

In paragraph 6 of the petition, it has been stated that the petitioner had completed nearly 95% of the work till date of filing of the petition. From paragraph 11 of the counter affidavit filed on behalf of the respondents by the E.E., CPWD, GCD, it appears from a plain reading thereof that the specific assertion made by the petitioner in paragraph 6 of the petition of having completed nearly 95% of the total work till date, has not been specifically denied.

Be that as it may, it appears that the petitioner sent several letters to the E.E., CPWD, GCD, requesting for issuance of completion certificate and closure of the contract. From paragraph 14 of the counter affidavit, it appears that there have been several correspondences from the end of the concerned respondent authority also, requesting the petitioner to complete the pending work but according to the respondent, the petitioner had repeatedly neglected to complete the work.

In this factual backdrop, it appears that the petitioner invoked the arbitration clause, initially by writing to the E.E., CPWD, GCD, on 23[rd]November, 2021, and subsequently, on 27[th] November, 2021, to the Chief Engineer, Central Public Works Department, Matigara, Siliguri, being the authority to appoint an Arbitrator in terms of clause 25 of the General Clauses of Contract governing the parties.

A bare perusal of clause 25, however, reveals inter alia that in terms of the contract, each party invoking arbitration must exhaust the prescribed alternative mechanism of settlement of claims/disputes prior to invoking arbitration. This alternative mechanism which has been clearly specified in clause 25 is named as the Dispute Redressal Committee (DRC). Clause 25 further reveals that even before the DRC is constituted, it is the duty of the concerned Engineer to give his instructions or decision in writing within a period of one month from receipt of the contractor’s letter. In so far as the instant matter is concerned, all the concerned respondent authorities have remained silent and have not taken any step for redressal of the grievances sought to be raised by the petitioner.

pm/ami

In such circumstances, this Court is of the view that the Chief Engineer of Central Public Works Department, Matigara, Siliguri, may be directed to consider the petitioner’s letters which have been referred to in the instant arbitration petition and take a decision supported with cogent reasons, within a period of 30 days from date. In the event, the petitioner is dissatisfied with such decision, it will be at liberty to appeal against the same before the Dispute Redressal Committee (DRC), within a period of 36 days therefrom in terms of clause 25 of the contract. Such appeal shall be disposed of by the Dispute Redressal Committee (DRC), within a period of 90 days from the date of receipt of the petitioner’s appeal, also in terms of the said clause 25. In the event, the petitioner is dissatisfied with the decision to be rendered by the Dispute Redressal Committee (DRC), it will be at liberty to take further steps in the matter in terms of clause 25 of the contract, which governs both the parties. The arbitration application stands disposed of accordingly.

(Biswanath Somadder) Chief Justice

You have used today's free searches. Sign in, for free, to keep searching without a limit.

Compass reads the judgments for you and finds the paragraphs for and against your question. Sign in to use it.

My Vault follows judgments for you and records every later decision that cites them. Sign in to keep one.

Sign in to download the court's PDF. The full text stays free to read here.

Sign in, for free, to download the court copy. Reading the full text here stays open to everyone.

Search and read Indian judgments without limits, save them to My Vault and find the relevant paragraphs with Compass.

Open the sign-in page instead